259. To ask the Minister for Rural and Community Development the capital allocation across his Department in each of the years 2018 to 2022. [20456/18]

Photo of Jonathan O'BrienJonathan O'Brien (Cork North Central, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

260. To ask the Minister for Rural and Community Development his Department's capital allocation for projects underway and projects already tendered or committed to spending contractually. [20473/18]

Photo of Jonathan O'BrienJonathan O'Brien (Cork North Central, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

261. To ask the Minister for Rural and Community Development his Department's capital allocation in each of the years 2018 to 2022 disaggregated according to capital allocated to projects underway, projects contractually committed to and projects yet to be initiated. [20490/18]

Photo of Michael RingMichael Ring (Mayo, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 259 to 261, inclusive, together.

My Department’s Capital allocation to 2022 is as follows:

-2018 2019 2020 2021 2022
Total Capital Allocation88* 141 150 152 175

* + 7.7 Capital Carryover

My Department provides funding at programme level to support local authorities and others in the delivery of individual projects. In respect of allocations for 2018, the breakdown of my Department’s capital spend at programme level is as follows.

Capital allocations

-€,000
Administration302
A3Dormant Accounts2006
A5National Rural Development Schemes15383
A6LEADER35000
A8Town and Village Regeneration Scheme15000
A9Rural Broadband, Regional Economic Development600
A10Local Improvement Scheme10000
B6RAPID3767
B8Programme for Peace and Reconciliation700
B10Library Development and Archive Service2750
B11Community Facilities Fund2000

In general, the breakdown of capital funding for my Department between subheads is agreed annually as part of the Estimates process. In the case of the LEADER programme, the overall allocation for this programme for the period 2014-2020 has been agreed at €250 million as part of the EU co-funded Rural Development Programme 2014-2020.

Details of individual projects supported by my Department are available on my Department’s website.

As recently announced, a new Rural Regeneration and Development Fund will be established under my Department as part of Project Ireland 2040. The fund will invest an additional €1 billion in supporting rural renewal. The additional investment under the Rural Regeneration and Development Fund will commence in 2019 and will ramp up incrementally over the first 4 years before reaching a steady level of investment.

My Department is currently developing proposals for the detailed operation of the Rural Regeneration and Development Fund, and I will announce the details following consultation with relevant Government colleagues.