Written answers

Tuesday, 27 March 2018

Department of Education and Skills

Schools Building Projects Data

Photo of Thomas ByrneThomas Byrne (Meath East, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

256. To ask the Minister for Education and Skills the number of school building projects that have been required to apply to local authorities for an extension of duration of planning permission due to delays; and the detail of each. [13758/18]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Seven major school building projects at Architectural Planning Stage have been required to apply to local authorities for an extension of duration of planning permission due to delays. The detail of each project are listed in the attached spreadsheet.

While it is a rare occurrence, it can happen that a project may experience delays following a grant of planning permission for a number of reasons. For example, a need to appoint a replacement architect or engineer on the design team, a legal challenge to a grant of planning permission, delays in securing a site or an extension to a site and changes sought in the brief by the school following the grant of planning permission. In some cases the delay can be attributable to an underperforming design team.

Included on the attached spreadsheet are two projects where an extension of planning permission has been sought and a decision is currently awaited from the Local Authority.

CountyRoll NoSchoolDate Grant of PP extended fromComment re delays
Cavan19439BHoly Family Special School
12/01/18
Changes to brief by the school following the grant of planning permission, need to appoint a replacement M&E engineer on the design team and delays while various decant proposals explored.
Longford19429VSt. Christopher's Special School
17/07/17
Issues with Design Team
Donegal19927OScoil Mhuire Stranorlar
12/05/17
Site acquired with conditional planning permission. Revised Brief Formulation Report necessary to take account of PP conditions imposed. Fire Safety Certificate appealed to An Bord Pleanála.
Cork19415KScoil An athar Tadhg
09/01/18
Significant changes proposed by school to scope of project.
Cork19993EGaelscoil An Ghoirt Álainn
08/12/16
Planning Permission appealed to An Bord Pleanála twice & a legal challenge to Planning Permission pending acquisition of site.
CountyRoll NoSchoolExtension of PP application with Local Authority with effect fromComment re delays
Meath17705JWhitecross
22/01/18
Full grant of Planning Permission received 13/1/14. Delays occurred due to school submitting various options for temporary decant and subsequent need to apply for statutory approvals for temporary decant off site.
Meath18106PLismullen
19/02/18
Full grant of Planning Permission received 13/9/13. Issues with the Design Team contributed to delays.