Written answers

Tuesday, 20 March 2018

Department of Public Expenditure and Reform

Minor Flood Mitigation Works and Coastal Protection Scheme Data

Photo of Bernard DurkanBernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

154. To ask the Minister for Public Expenditure and Reform the applications submitted to the Office of Public Works by a local authority (details supplied) in each of the past three years to address flooding problems under the minor works flood relief fund; if it is open to the local authority to submit minor works applications for areas included in the CFRAM reports; and if he will make a statement on the matter. [12579/18]

Photo of Kevin  MoranKevin Moran (Longford-Westmeath, Independent)
Link to this: Individually | In context | Oireachtas source

I am advised that the Flood Risk Management Plans under the CFRAM Programme which are due to be submitted shortly to the Minister for Finance and Public Expenditure and Reform for approval include a number of proposed projects which fall within the financial threshold of the Minor Works scheme, that is, up to an estimated cost of €750,000. On approval of the Plans by the Minister, these minor projects can be progressed by the Local Authorities with full funding from the OPW. If there are other localised minor works identified by Local Authorities within the areas covered by the CFRAM Plans then I am advised that it is open to the Local Authorities to submit applications under the Minor Flood Mitigation Works and Coastal Protection scheme for those works. All applications will be considered within the criteria of the scheme.

Please see listed in tabular form the applications submitted under the Minor Flood Mitigation Works and Coastal Protection scheme by Mayo County Council in 2016, 2017 and 2018 to date.

Project LocationProject DetailsApproved FundingYear of Approval/Application
Salmon Leap Cottage, BelclareDivert flood waters away from house back into main channel€9,0002016
Crossmolina  Car ParkTo remove existing railing, construct wall and flood barrier and associated works€95,2202016
Crossmolina WalkwayTo remove existing shrubbery, construct walls, supply and install flood gate & associated works€64,3502016
Crossmolina  Chapel StreetTo re point/repair existing stone wall€29,7002016
Copper Beach, StraideRaise embankment at site- 35m embankment 5600 high with slopes 1:1 €5,4902016
Carrowbeg River, WestportStudyAwaiting outcome of CFRAM
Seasonmaster, Straide175m long raised embankment at site perimeter. Raise road surface above adjacent watercourse €28,5752016
Bachelor's Walk, BallinaConstruction of land bankAwaiting outcome of CFRAM
Green Road, FoxfordProvide demountable flood barriersunder considerationFurther information requested by OPW -2016
Blacksod Harbour, BelmulletCoastal erosion risk management studyunder considerationFurther information requested by OPW- 2016
Bunafolly, DoohomaCoastal erosion risk management studyunder considerationFurther information requested by OPW -2016
Portacloy Beach, Belmullet (coastal)Coastal erosion risk management studyunder considerationFurther information requested by OPW - 2016
Rinroe, Kilgalligan, Carrowteigue (coastal)Coastal erosion risk management studyunder considerationFurther information requested by OPW - 2016
Shore Road, School Road, Belmullet (coastal)Coastal flooding risk management studyunder considerationFurther information requested by OPW - 2016
BallyhankeenDeepen existing & excavate new open drains and upgrade culverts€56,7652017
BunnadoberDeepen, widen and extend the existing road side open drain. Extend the road side embankment. Construct a culvert and install an opening (new gates, series of pipes)€138,0792017
Crossmolina, Chapel StreetTo re point/repair existing stone wall€12,2072017
Cong and DrumsheelUndertake structural assessment of existing river wall and road. Remove the super structure from Cong weir and install/improve safety fencing.

Upgrade river wall and install an emergency overflow/storm pump and 3 flood gates
€324,8192017
Neale/Cross Flood Relief Scheme.Study for pre-feasibility study, feasibility study and preferred options.Under consideration 2018