374. To ask the Minister for Health the primary care centre projects announced on 17 July 2012, in tabular form; the status of each; and if he will make a statement on the matter. [8527/18]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Delivery of primary care infrastructure is a dynamic process, which evolves to take account of changing circumstances including the feasibility of implementation.

The table below gives details of the 35 locations announced on 17 July 2012, and their current status including estimated opening dates. Five of these primary care centres are already operational and eleven are projected to open by the end 2018.

In addition, it should be noted that 67 primary care centres have been opened since 2011, and a further 6 primary care centres are projected to open in 2018, in addition to those shown in the table below.

CountHSE RegionCountyLocation / PCT NameDelivery MethodProject Status - Q4 2017
1DMLDublin Rowlagh / North ClondalkinDirect buildStage 2a design team report completed. Purchase agreement finalised with adjoining school, subject to planning permission being granted for the development. HSE awaiting letter from Dept of Education in order to submit planning application.
2DMLDublin Curlew Road / Crumlin / DrimnaghDirect buildPlanning permission in place. Options being reviewed following reconfiguration of services in the area.
3DMLDublin Knocklyon / RathfarnhamDirect buildPlanning permission in place. Purchase of site being progressed.
4DMLWicklowRathdrum Operational LeasePlanning approved for retrofit of existing building, but now needs new building. Discussions ongoing with developer.
5DMLKildareKilcockPPPConstruction complete. Projected opening Q1 2018
6DNEDublin Coolock / DarndalePPPConstruction nearing completion. Projected opening Q2 2018
7DNEDublin Summerhill, north inner city DublinPPPIn construction. Projected opening Q3 2018
8DNEDublin BalbrigganOperational LeaseOperational since Q3 2017
9DNEDublin SwordsOperational LeasePreferred bidder selected. Letter of Intent issued August 2017.
10DNELouthDrogheda northOperational LeaseExisting building requires fitout. Projected completion Q1 2018 and operational Q2 2018.
11DNEMeathLaytown and BettystownOperational LeaseRe-advertised in November 2017. Submissions received, currently under review.
12DNEMeathKellsOperational LeaseOperational since Q1 2016
13DNEMonaghanCarrickmacrossOperational LeaseLayouts agreed. Finalising Agreement for Lease.
14SouthCarlowTullow / Rathvilly / HacketstownDirect buildAdjoining landowner has re-engaged with HSE. Options being reviewed.
15SouthKilkennyKilkenny city (East)Operational LeaseLetter of Intent issued. Layouts being reviewed. Legal discussions progressing.
16SouthWexfordWexford townPPPIn Construction. Projected opening Q2-Q3 2018
17SouthWaterfordDungarvanPPPIn Construction. Projected opening Q2-Q3 2018
18SouthWaterfordWaterford city (east)PPPIn Construction. Projected opening Q2-Q3 2018
19SouthCorkCork city - Ballyphehane / Togher / Greenmount / The LoughOperational LeaseLetter of Intent issued. Layouts being developed. Planning in discussion with local authority.
20SouthKerryTraleeOperational LeaseLetter of Intent issued. Layouts being reviewed. Planning permission received.
21SouthTipperaryCarrick-on-SuirPPPIn Construction. Projected opening Q2 2018
22SouthTipperaryClonmelOperational LeaseReviewing accommodation requirements before progressing to stage 3. Existing HSE facilities being reviewed.
23WestTipperaryThurlesOperational LeaseLetter of Intent issued. Agreement for Lease signed. Planning application submitted.
24WestLimerickLimerick city (Ballinacurra / Weston)PPPOperational Q1 2018
25WestClareEnnisOperational LeaseStage 3 priced offers being evaluated.
26WestGalway TuamPPPOperational since Q4 2017.
27WestGalway GortOperational LeaseLetter of Intent withdrawn 24/05/2016. Possible re-advertisement.
28WestRoscommonBoylePPPOperational Q1 2018
29WestRoscommonBallaghadereenOperational LeaseLetter of Intent issued 27/10/2015. Project progressing to Agreement for Lease.
30WestMayoWestportPPPIn Construction. Projected opening Q2 2018
31WestMayoClaremorrisPPPConstruction complete. Projected opening Q1 2018
32WestSligoBallymotePPPConstruction complete. Projected opening Q1 2018
33WestDonegalAn Clochán Liath - DungloeOperational LeaseRe-advertised for Operational Lease option. Expressions of interest received. Stage 2 responses received, preparing to issue stage 3 letters.
34WestDonegalDonegal townOperational LeaseExpressions of interest received. Currently being reviewed

* Coolock and Darndale were announced as two separate locations