Schools Building Projects Status

Photo of Joan BurtonJoan Burton (Dublin West, Labour)
Link to this: Individually | In context | Oireachtas source

212. To ask the Minister for Education and Skills when tenders will be invited for a project (details supplied); the closing date for receipt of tenders; if they have been invited; when construction of the new school is likely to commence; and if he will make a statement on the matter. [5908/18]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The school building project to which the Deputy refers is currently at advanced architectural planning stage. It is anticipated that tenders for the school will be invited in Q1 2018 with construction anticipated to commence in Q2 2018.

Photo of Joan BurtonJoan Burton (Dublin West, Labour)
Link to this: Individually | In context | Oireachtas source

213. To ask the Minister for Education and Skills if his Department has received a revised stage 2(b) report for a project (details supplied); when tenders will be invited for the project; when construction of the new school is likely to commence; and if he will make a statement on the matter. [5909/18]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The building project referred to by the Deputy is for a new 24 classroom school including a Special Needs Unit, with a floor area of approx. 4,748m2.

The project is currently at Stage 2B of Architectural Planning - Detailed Design Stage, which includes applications for all statutory consents, including Planning Permission, Disability Access Certificate and Fire Safety Certificate and also the preparation of tender documentation. Planning Permission for this project was received in August 2017.

The Stage 2B report has just recently been received and reviewed by my Department. A number of issues were identified as needing clarification by the Design Team prior to approval of the Stage 2B submission.

Once a revised Stage 2B submission which addresses these issues has been received and reviewed, my Department will then revert to the school with regard to a timeframe for progression to tender.