484. To ask the Minister for Communications, Climate Action and Environment if the national broadband plan formal procurement process has now been completed in respect of rollout to a location (details supplied); the timeframe within which a broadband upgrade will be provided; and if he will make a statement on the matter. [3302/18]

Photo of Denis NaughtenDenis Naughten (Roscommon-Galway, Independent)
Link to this: Individually | In context | Oireachtas source

The Government's National Broadband Plan (NBP) aims to ensure high speed broadband access (minimum 30 megabits per second) to all premises in Ireland, regardless of location.  The NBP has been a catalyst in encouraging investment by the telecoms sector so that today over 67% of the 2.3m premises in Ireland have access to high speed broadband and this is set to increase to 77% (1.8m premises) by the end of 2018 and to 90% (2.1m premises) by the end of 2020.  In April I published an updated High Speed Broadband Map which is available at www.broadband.gov.ie. This map shows the areas targeted by commercial operators to provide high speed broadband services and the areas that will be included in the State Intervention Area under the NBP.

The Map is colour coded and searchable by address/eircode:

- The AMBER areas represent the target areas for the proposed State led Intervention under the NBP and are the subject of an ongoing  procurement process. 

- The BLUE represent those areas where commercial providers are either currently delivering or have plans to deliver high speed broadband services. 

- The Light BLUE areas represent eir's commercial rural deployment plans to rollout high speed broadband to 300,000 premises by the end of 2018 as part of a Commitment Agreement signed with me in April.

There are 56 premises in Richardstown. 31 (55%) fall within the AMBER area and will be covered under the State led Intervention. 19 (34%) premises are in a BLUE area and are or will be covered by commercial providers, while 6 (11%) are LIGHT BLUE and fall to be covered by eir's planned rural deployment.

My Department is in a formal procurement process to select a company or companies who will roll-out a new high speed broadband network in the State intervention area. That procurement process is now at an advanced stage. “Detailed Solutions” submitted by two bidders on 26th September are being evaluated by the NBP specialist team. This is the last stage of the procurement process before moving to the final tender stage, which will be followed by the appointment of a preferred bidder(s) and contract signature.

In the interim, practical initiatives will continue to be addressed through the work of the Mobile Phone and Broadband Taskforce to address obstacles and improve connectivity in respect of existing and future mobile phone and broadband services.

Under this Taskforce, engagement between telecommunications operators and local authorities through the Broadband Officers is continuing to strengthen.  These Broadband Officers are acting as single points of contact in local authorities for their communities.  The appointment of these officers is already reaping rewards in terms of ensuring a much greater degree of consistency in engagements with operators and clearing obstacles to developing infrastructure.  There is a link to a list of these local Broadband Officers on my Department's website.