Written answers

Wednesday, 29 November 2017

Department of Education and Skills

Schools Building Projects Status

Photo of Joan BurtonJoan Burton (Dublin West, Labour)
Link to this: Individually | In context | Oireachtas source

133. To ask the Minister for Education and Skills if he has completed the schedule of accommodation requirements for the extension to a school (details supplied) in County Kildare; if completed, the accommodation requirements agreed; if not, when the schedule will be completed; when a design team will be appointed for the project; and if he will make a statement on the matter. [50839/17]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Deputy will be aware that a building project for the school in question is included in my Department's 6 Year Construction Programme.

Following the site visit to the school by my Department, the preliminary work associated with the project has been initiated. This includes determining how the accommodation needs of the school will be met and this process is in train. My Department will be in further contact with the school patron when this process has been completed.

Photo of Joan BurtonJoan Burton (Dublin West, Labour)
Link to this: Individually | In context | Oireachtas source

134. To ask the Minister for Education and Skills if the invitation to tender for a new school (details supplied) in County Kildare has been sanctioned; and if he will make a statement on the matter. [50841/17]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Design Team for the major building project for the school in question submitted the original Stage 2B Report in August of this year and my Department found a number of omissions in this report. The original report was returned to the Design Team via the Board of Management for updating. 

An amended Stage 2B report has recently been received and is currently being reviewed by my Department. 

On completion of the review of this report, my Department will revert to the Board of Management with regard to the further progression of the project at that time.

Photo of Joan BurtonJoan Burton (Dublin West, Labour)
Link to this: Individually | In context | Oireachtas source

135. To ask the Minister for Education and Skills if the stage 2B documents including tender documents for a new school (details supplied) in County Kildare have been submitted to his Department for approval; and if he will make a statement on the matter. [50842/17]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The project referred to by the Deputy has been devolved for delivery to Kildare and Wicklow Education and Training Board (ETB).

My Department has not received the Stage 2B documents. I understand from the ETB that they will be submitted shortly.

Photo of Joan BurtonJoan Burton (Dublin West, Labour)
Link to this: Individually | In context | Oireachtas source

136. To ask the Minister for Education and Skills if the invitation to tender for a new school (details supplied) in County Kildare has been sanctioned; and if he will make a statement on the matter. [50843/17]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Design Team for the major building project for the school in question submitted the original Stage 2b Report in September of this year and my Department found omissions in this report. The original report was returned to the Design Team via the Board of Management for updating. 

An amended Stage 2B report has recently been received and this is currently being reviewed by my Department. 

On completion of the review of this report my Department will revert to the Board of Management with regard to the further progression of the project at that time.

Comments

No comments

Log in or join to post a public comment.