Written answers

Tuesday, 24 October 2017

Department of Housing, Planning, and Local Government

Social and Affordable Housing Data

Photo of John CurranJohn Curran (Dublin Mid West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

416. To ask the Minister for Housing, Planning, and Local Government the number of rapid-build houses that have been built and occupied to date; the further schemes that are expected to be completed in 2017; and if he will make a statement on the matter. [44742/17]

Photo of Eoghan MurphyEoghan Murphy (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

In addition to the 22 rapid build houses completed in Poppintree in 2016, additional houses have now been completed and occupied or are in the process of being allocated in St. Helena’s Drive, Finglas (39 social homes) and Hansfield, Dublin 15 (36 social homes). Details of other schemes due for completion in 2017 and early/mid 2018 are as follows:

Cherry Orchard, Ballyfermot 24 homes, scheduled for completion and allocation in November 2017
Mourne Road, Drimnagh29 homes, scheduled for completion and allocation in November 2017
Belcamp, Dublin 1738 homes, scheduled for completion and allocation in November 2017
Wellview, Mulhuddart20 homes, scheduled for completion and allocation in November / December 2017
Woodbank and Rathvilly, Finglas17 homes, scheduled for completion and allocation end 2017/early 2018
Cherry Orchard, Ballyfermot53 homes, scheduled for completion and allocation end 2017/early 2018
St. Aidan’s, Brookfield, Tallaght71 homes, scheduled for delivery Q2 2018 and Q3 2018
Pinewood, Balbriggan25 homes, scheduled for delivery Q1 2018
George’s Place, Dun Laoghaire12 homes, scheduled for delivery in early 2018
Avondale, Mulhuddart44 homes (20 units scheduled for delivery in Q2 2018 & 24 in Q 3 2018)
Killininny Road, Firhouse24 homes scheduled for delivery in Q3 2018
St Cuthbert’s, Clondalkin, South Dublin59 homes scheduled for delivery in Q4 2018

My Department recently asked all local authorities to review the social housing projects in their areas and in the interest of achieving earliest delivery, they have been requested to consider their suitability for Design and Build contracts under the Rapid Build Framework set up by the Office of Government Procurement. They were asked to consider, in particular, schemes which are amenable to early commencement, particularly in terms of their approved planning status. In response, some authorities have indicated that a number of both approved schemes and additional schemes under consideration may be suitable and I expect to be in a position to announce details of these additional schemes shortly.