Written answers
Monday, 11 September 2017
Department of Housing, Planning, and Local Government
Local Authority Housing Data
John Curran (Dublin Mid West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
2033. To ask the Minister for Housing, Planning, and Local Government the number of rapid build houses which have been built to date; the additional number expected to be completed by the end of 2017; and if he will make a statement on the matter. [38211/17]
Eoghan Murphy (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source
Following the completion of 22 rapid build houses in Poppintree in 2016, an additional 21 houses have now been completed and occupied in St. Helena’s Drive, Finglas. Details of other schemes due for completion in 2017 and 2018 are as follows:
Cherry Orchard, Ballyfermot | 24 homes, scheduled for completion and allocation in September 2017 |
---|---|
Mourne Road, Drimnagh | 29 homes, scheduled for completion and allocation in September 2017 |
St. Helena’s, Finglas | 21 homes allocated, 18 remaining on the site are scheduled for completion and allocation in September 2017 |
Belcamp, Dublin,17 | 38 homes, scheduled for completion and allocation September 2017 |
Wellview, Mulhuddart | 20 homes, scheduled for completion and allocation in November / December 2017 |
Woodbank, Rathvilly | 17 homes, scheduled for completion and allocation end 2017/early 2018 |
Cherry Orchard, Ballyfermot | 53 homes, scheduled for completion and allocation end 2017/early 2018 |
St. Aidan’s, Brookfield | 71 homes, scheduled for delivery Q2 2018 and Q3 2018 |
Pinewood, Balbriggan | 25 homes, scheduled for delivery Q1 2018 |
George’s Place, Dun Laoghaire | 12 homes, scheduled for delivery in early 2018 |
Avondale, Mulhuddart, Fingal | 44 homes (20 units scheduled for delivery in Q2 2018 & 24 in Q 3 2018) |
Killininny Road, Firhouse, South Dublin | 24 homes scheduled for delivery in Q3 2018 |
St Cuthberts, Clondalkin, South Dublin | 59 homes scheduled for delivery in Q4 2018 |
Hansfield, Dublin 15 | 36 homes, outline design and costs currently being prepared |
My Department has recently asked all Local Authorities to review the social housing projects in their areas and in the interest of achieving earliest delivery, they have been requested to consider their suitability for Design and Build contracts under the Framework set up by the Office Of Government Procurement. They are being asked to consider, in particular, schemes which are amenable to early commencement, particularly in terms of their approved planning status.
No comments