Department of Communications, Energy and Natural Resources

North-South Interconnector

Photo of Niamh SmythNiamh Smyth (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

1722. To ask the Minister for Communications, Energy and Natural Resources if he will redraft the terms of reference for the North-South Interconnector to reflect the wishes of the persons in the areas of counties Cavan and Monaghan affected and two groups (details supplied) as per the Fianna Fáil Dáil Éireann motion which was passed in 2017; and if he will make a statement on the matter. [27426/17]

Photo of Denis NaughtenDenis Naughten (Roscommon-Galway, Independent)
Link to this: Individually | In context | Oireachtas source

On 19 December 2016 An Bord Pleanála granted planning permission for the North-South Interconnector project in Ireland. The decision concluded a lengthy planning process which included an Oral Hearing completed over eleven weeks from March to May last year. The planning decision is currently the subject of Judicial Review proceedings. The planning process for the section of the project in Northern Ireland is ongoing with an oral hearing concluding on 27 February 2017. In light of the motions passed by Dáil Éireann and Seanad Éireann, I have had proposals prepared for an updated independent study. In preparing the terms of reference for this study, my officials held meetings with representatives of the North East Pylon Pressure Campaign on 28 March and the Monaghan Anti-Pylon Committee on 3 April. This engagement was important in facilitating local representative groups input into the terms of reference drafting process.

I approved the Terms of Reference for the study and published them on my Department's website on Monday 8 May. This study will bring further clarity to the relative cost and technical merits of overhead and underground solutions for the North South Interconnector.

Following the publication of the Terms of Reference, I met with the Deputy and a number of other Oireachtas members from Cavan, Monaghan and Meath on Tuesday 16 May. This meeting provided me the opportunity to update the members on progress in relation to the proposed study and for the members to provide feedback.

As discussed at that meeting, it is not proposed to include external factors (such as local tourism, health, landscape, agriculture and heritage). These were examined as part of the statutory planning process which is the appropriate method by which such impacts are assessed and evaluated and therefore there are no plans to re-draft the terms of reference.

The impact on land and property values and the level of compensation paid in lieu of such impacts was also discussed at the meeting with Oireachtas members and at the meetings with the community groups referred to in the question. Whilst it would not be appropriate for me to intrude on settled processes for addressing these issues between developers and affected landowners, in light of the concerns that have been voiced, I am commissioning  research on international comparative practice on the approach to and levels of compensation provided to land and property owners in proximity to high-voltage power lines.