420. To ask the Minister for Health further to Parliamentary Question No. 201 of 10 May 2017, the details for each of the 90 designated centres due to comply with 2021 regulations; the proposed scheduling of works in respect of each centre; and the stage each of the designated centres is at in respect of the works in question. [23987/17]
Helen McEntee (Meath East, Fine Gael)
Link to this: Individually | In context | Oireachtas source
Significant work has been undertaken by the HSE in determining the most appropriate scheduling of projects over the multi-annual period from 2016 to 2021, within the phased provision of funding, to achieve compliance and registration. All healthcare infrastructure developments, including this development, must comply with DPER guidelines and EU directives and will require a lead-in time to complete the various stages. These stages include appraisal, project brief, design feasibility, detailed design, some of which may overlap, the review of costing estimates and finalisation of financing.
The following table shows the status of the various projects at Q1/2017. Replacement accommodation for some facilities will be combined in a single location.
County | Facility | Status at Q1 2017 | Projected construction completion | |
---|---|---|---|---|
1 | Cavan | Lisdaran Unit for the Elderly, Cavan GH | Operational | n/a |
2 | Cavan | Ballyconnell Community Services | Detailed Design | Q1, 2019 |
3 | Donegal | Killybegs CNU | Detailed Design | Q1, 2017 |
4 | Donegal | An Fál Carrach/Falcarragh CNU | Detailed Design | Q2, 2020 |
5 | Donegal | Buncrana CNU | Detailed Design | Q4, 2018 |
6 | Donegal | An Clochán Liath/Dungloe Community Hospital | Detailed Design | Q3, 2018 |
7 | Donegal | Carndonagh Community Hospital | Detailed Design | Q2, 2019 |
8 | Donegal | Letterkenny CNU to replace Lifford | Design Feasibility | Q3, 2021 |
9 | Donegal | Letterkenny CNU to replace Ramelton | Design Feasibility | Q3, 2021 |
10 | Donegal | Letterkenny CNU to replace St. Joseph's | Design Feasibility | Q3, 2021 |
11 | Donegal | Ballyshannon CNU to replace The Rock CNU | Design Feasibility | Q4,2019 |
12 | Donegal | Ballyshannon CNU to replace Shiel Hospital | Design Feasibility | Q4,2019 |
13 | Leitrim | St. Patrick's Hospital, Carrick-on-Shannon | Design Feasibility | Q3, 2021 |
14 | Monaghan | St Mary's, Castleblaney | Operational | n/a |
15 | Monaghan | Oriel House, Monaghan | Design Feasibility | Q4, 2018 |
16 | Sligo | Nazereth House, Ballymote (extension) | Tender & Contract | Q1, 2018 |
17 | Sligo | St John's Community Hospital, Sligo | Phased delivery | Q4, 2019 |
18 | Galway | Áras Mhic Dara, An Cheathrú Rua/ Carraroe | Operational | n/a |
19 | Galway | Áras Rónáin, Inis Mór/Aran Islands | Detailed Design | Q4, 2017 |
20 | Galway | Áras Mhuire, Tuam | Appraisal | Q4, 2021 |
21 | Galway | St Anne's CNU, Clifden | Appraisal | Q4, 2021 |
22 | Galway | Merlin Park, Units 5 & 6 | Appraisal | Q4, 2021 |
23 | Mayo | St Augustine's, Ballina | Operational | n/a |
24 | Mayo | McBride CNU, Westport | Operational | n/a |
25 | Mayo | Dalton Home, Claremorris | Operational | n/a |
26 | Mayo | St Fionnán's CNU, Acaill/Achill | Operational | n/a |
27 | Mayo | Sacred Heart Hospital, Castlebar | Construction | Q4, 2017 |
28 | Mayo | Áras Deirbhile, Béal an Mhuirthead/ Belmullet | Construction | Q1, 2017 |
29 | Roscommon | Plunkett CNU, Boyle | Operational | |
30 | Roscommon | Áras Mháthair Phóil CNU, Castlerea | Operational | n/a |
31 | Roscommon | Sacred Heart Hospital, Roscommon | Appraisal | Q3, 2021 |
---|---|---|---|---|
32 | Clare | Regina House, Kilrush (Phase 2) | Operational | n/a |
33 | Clare | Ennistymon CNU (Phase 2) | Operational | n/a |
34 | Clare | Raheen CNU | Construction | Q2, 2019 |
35 | Clare | St Joseph's CNU, Ennis | Appraisal | Q1, 2021 |
36 | Limerick | St. Ita's, Newcastle West | Detailed Design | Q4, 2018 |
37 | Limerick | St. Camillus', Limerick | Design Feasibility | Q2, 2021 |
38 | Tipperary | St Conlon's CNU, Nenagh | Appraisal | Q3, 2020 |
39 | Tipperary | Dean Maxwell CNU, Roscrea | Appraisal | Q2, 2021 |
40 | Cork | Bandon Community Hospital | Construction | Q3, 2017 |
41 | Cork | Kinsale -3 phases; phase 1 completed. | Construction | Phase 3 completed by 2020 |
42 | Cork | Bantry General Hospital | Construction | Q1, 2017 |
43 | Cork | Dunmanway CH (St. Anthony's) | Construction | Q1, 2017 |
44 | Cork | Cois Abhainn, Youghal | Construction | Q2, 2017 |
45 | Cork | St Patrick's CH, Fermoy | Detailed Design | Q4, 2018 |
46 | Cork | Skibereen CH (St Anne's) | Detailed Design | Q3, 2018 |
47 | Cork | St Joseph's CH, Millstreet | Detailed Design | Q1, 2019 |
48 | Cork | Youghal Community Hospital | Detailed Design | Q1, 2019 |
49 | Cork | Castletownbere CH (St. Joseph's) | Detailed Design | Q4, 2017 |
50 | Cork | Middleton CH & Long Stay Unit | Appraisal | Q3, 2021 |
51 | Cork | Clonakilty CH & Long Stay (Mount Carmel) | Appraisal | Q2, 2020 |
52 | Cork | Kanturk Community Hospital | Design Feasibility | Q1, 2019 |
53 | Cork | Cork City (St. Finbarr's) | Design Feasibility | Q1, 2021 |
54 | Cork | Macroom Community Hospital | Design Feasibility | Q2, 2019 |
55 | Kerry | Listowel Community Hospital | Detailed Design | Q4, 2018 |
56 | Kerry | Cahersiveen Community Hospital | Appraisal | Q3, 2020 |
57 | Kerry | Killarney CNU (St. Columbanus) | Appraisal | Q4, 2021 |
58 | Carlow | Sacred Heart Hospital, Carlow | Detailed Design | Q1, 2019 |
59 | Kilkenny | St Columba's Hospital, Thomastown | Appraisal | Q3, 2021 |
60 | Tipperary | St Patrick's Hospital, Cashel | Appraisal | Q3, 2021 |
61 | Waterford | St Patrick's Hospital, John's Hill, Waterford City | Tender & Contract | Q1, 2019 |
62 | Waterford | St Joseph's & Dungarvan Community Hospital (all phases) | Detailed Design | Q4, 2021 |
---|---|---|---|---|
63 | Wexford | New Houghton Hospital, New Ross | Appraisal | Q3, 2018 |
64 | Wexford | Gorey District Hospital (phased) | Appraisal | Q1, 2019 |
65 | Dublin | Dalkey CNU, South Dublin | Detailed Design | Q3, 2019 |
66 | Dublin | Leopardstown Park Hospital | Appraisal | Q2, 2021 |
67 | Dublin | Royal Hospital, Donnybrook | Appraisal | Q1, 2020 |
68 | Wicklow | St Coleman's, Rathdrum | Design Feasibility | Q3, 2021 |
69 | Dublin | Bellevilla CNU, South Circular Road | Equipping & Commissioning | Q1, 2017 |
70 | Dublin | Tymon North, Tallaght (replacing Crooksling) | Tender & Contract | Q3, 2019 |
71 | Dublin | Peamount Hospital, Newcastle | Tender & Contract | Q1, 2019 |
72 | Dublin | Meath Hospital CNU | Detailed Design | Q1, 2019 |
73 | Dublin | Our Lady's Hospice, Harold's Cross | Appraisal | Q4, 2021 |
74 | Dublin | Cherry Orchard Hospital | Appraisal | Q3, 2021 |
75 | Kildare | St. Vincent's, Athy | Appraisal | Q4, 2021 |
76 | Wicklow | Baltinglass Community Hospital | Construction | Q2, 2017 |
77 | Laois | St Vincent's, Mountmellick | Operational | n/a |
78 | Longford | St Joseph's Care Centre, Longford (phased) | Construction | Q2, 2021 |
79 | Louth | St. Oliver Plunkett, Dundalk | Construction | Q1, 2017 |
80 | Louth | St Joseph's Hospital, Ardee | Appraisal | Q3, 2021 |
81 | Louth | St Mary's Hospital, Drogheda | Appraisal | Q2, 2020 |
82 | Meath | St Joseph's, Trim | Operational | n/a |
83 | Offaly | Ofalia House CNU Edenderry | Construction | Q1, 2017 |
84 | Offaly | Riada House, Tullamore | Construction | Q1, 2018 |
85 | Westmeath | St Vincent's Care Centre, Athlone | Detailed Design | Q3, 2020 |
86 | Dublin | Seanchara combined with Clarehaven (Glasnevin) | Tender & Contract | Q3, 2018 |
87 | Dublin | Clarehaven combined with Seanchara (Glasnevin) | Tender & Contract | Q3, 2018 |
88 | Dublin | Connolly Hospital, Blanchardstown | Design Feasibility | Q2, 2021 |
89 | Dublin | Grangegorman to replace Chapel View, St. Mary's Hospital | Design Feasibility | Q2, 2021 |
90 | Dublin | Grangegorman to replace St. Clare's, Glasnevin | Design Feasibility | Q2, 2021 |