156. To ask the Minister for Housing, Planning, Community and Local Government the scheme of rapid build housing which will be completed next and ready for occupation; when this scheme will be complete; the number of units of accommodation which will be provided; and if he will make a statement on the matter. [23892/17]

Photo of Simon CoveneySimon Coveney (Cork South Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source

My Department is working closely with all local authorities in relation to increasing and accelerating the delivery of a range of social housing programmes and supports, including rapid build/delivery homes. At the end of 2016, a total of 350 rapid build homes were advancing through various stages of delivery, including construction, with 22 such homes being delivered and occupied in 2016. Over 500 rapid build homes are now advancing and work is underway at advancing a further 500 rapid build homes in 2017, with another 500 units to be delivered in 2018.

In relation to the 350 rapid build homes that were advancing at the end of 2016, the following are the 11 projects concerned:

ProjectsUnits of accommodation
George’s Place, Dun Laoghaire12 homes
St. Aidan’s, Brookfield71 homes
Poppintree, Ballymun22 homes (completed)
Cherry Orchard, Ballyfermot24 homes
Mourne Road, Drimnagh30 homes
St. Helena’s, Finglas39 homes
Belcamp, Dublin, 1738 homes
Cherry Orchard, Ballyfermot52 homes
Woodbank, Rathvilly18 homes
Wellview, Mulhuddart  20 homes
Pinewood, Balbriggan 24 homes

Of these projects, the following are currently on site and are due for completion this year:

ProjectsUnits of accommodationCompletion date
St.Helena’s, Finglas 39 homesJune
Mourne Road, Drimnagh30 homesJuly
Cherry Orchard24 homesJuly
Belcamp, Dublin 17  38 homesSeptember
Wellview, Mulhuddart20 homesNovember

It should be noted that Dublin City Council is in negotiation with the contractors in order to accelerate delivery and ensure a phased hand-over of these rapid build homes. The next phase of 70 rapid build homes will commence in Dublin City with the award of contracts in June 2017, with work then commencing on site. 

A further 5 schemes, which will deliver 177 units, were approved under the Rapid Delivery Programme in Quarter 1, 2017. They are:

ProjectsUnits of accommodation
Hansfield, Dublin 1536 homes
Avondale, Mulhuddart  44 homes
Killininney, Firhouse24 homes
St. Cuthberts, Clondalkin59 homes
Glenamuck/Rockville, Dun Laoghaire14 homes

I expect further projects, particularly in the Greater Dublin Area, to be brought forward shortly.