Written answers

Tuesday, 9 May 2017

Department of Education and Skills

Schools Building Projects Status

Photo of James LawlessJames Lawless (Kildare North, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

201. To ask the Minister for Education and Skills the status of progress for a new school build (details supplied); when it is expected a design team will be appointed; and if he will make a statement on the matter. [21635/17]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

As the Deputy is aware, a building project for the school to which he refers is included in the Department's 6-Year Construction Programme. In the context of progressing the building project, my Department has undertaken a site visit to the school. My Department is currently considering the options available to meet the school's accommodation needs and my Department will be in further contact with the school's Patron when this has been determined.  

Photo of James LawlessJames Lawless (Kildare North, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

202. To ask the Minister for Education and Skills the status of each new school build and school extension currently in progress across the north Kildare constituency; and if he will make a statement on the matter. [21636/17]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I wish to advise the Deputy that my Department does not hold the details requested by the geographical area to which he refers.

However, the current status of the 29 school building projects in County Kildare that are included on the Department's 6 Year Capital Programme is outlined in the attached table.

The Capital Programme also provides for devolved funding for additional classrooms to schools where an immediate enrolment need has been identified or where an additional teacher has been appointed. Responsibility for delivering such projects rests with the individual school authority.

Details of such funding approved in all schools, including Kildare, is available on my Department's website and this is updated regularly. 

Capital Programme – Major projects being progressed

CountyRoll NoSchool NameSchool typeStatus
Kildare16706GSt Joseph’s NS, KilcockPrimaryStage 2B
Kildare70680USt Conleth’s VS, NewbridgePost-PrimaryUnder construction
Kildare70700AMaynooth Community CollegePost-PrimaryStage 3
Kildare76193QNew Maynooth Community CollegePost-PrimaryStage 3
Kildare19277ASt Anne’s Special School, The CurraghSpecial SchoolStage 2A
Kildare19675NSt Brigid’s NS, KilcullenPrimaryCompleted
Kildare76194SNaas Community CollegePost-PrimaryStage 2B
Kildare76253ICelbridge Community CollegePost-PrimaryEarly Architectural Planning
Kildare20257CScoil Naomh Padraig, CelbridgePrimaryEarly Architectural Planning
Kildare15957DRathangan BNSPrimarySubstantial completion
Kildare61702DSt Paul’s Post-Primary SchoolPost-PrimaryStage 2A
Kildare15040TMercy Convent, NaasPrimaryStage 3
Kildare18288BScoil Mhichil Naofa, AthyPrimaryStage 2B
Kildare20428DGaelscoil Mhic Aodha, Kildare TownPrimaryUnder construction
Kildare19796CSt Patrick’s NS, ClanePrimaryStage 2B
Kildare15769C

16707I
Scoil Eimhinn Naofa & St Peter’s NS, MonasterevanPrimaryStage 2B
Kildare17341UMaynooth BNSPrimaryStage 2B
Kildare17872FSt Conleth’s & St Mary’s, NewbridgePrimaryStage 2A
Kildare17873HSt Conleth’s Infant SchoolPrimaryStage 2A
Kildare17254CSt Corban’s BNSPrimaryEarly Architectural Planning
Kildare18988GSt Raphael’s Special SchoolSpecial SchoolSite required
Kildare19455WSt Mark’s Special School, NewbridgeSpecial SchoolEarly Architectural Planning
Kildare20292EMaynooth ETNSPrimaryEarly Architectural Planning
Kildare61690WCross & Passion, KilcullenPost-PrimaryEarly Architectural Planning
Kildare70650LAthy Community CollegePost-PrimaryEarly Architectural Planning
Kildare70720GSt Farnan’s Post-Primary SchoolPost-PrimaryEarly Architectural Planning
Kildare13902OHewetson NSPrimaryEarly Architectural Planning
Kildare61681VPatrician Post-Primary, NewbridgePost-PrimaryEarly Architectural Planning
Kildare61730ISt Mary’s Girls Post-Primary School, NaasPost-PrimaryEarly Architectural Planning

Photo of Jan O'SullivanJan O'Sullivan (Limerick City, Labour)
Link to this: Individually | In context | Oireachtas source

204. To ask the Minister for Education and Skills the position regarding the construction of a new school (details supplied); when it is expected that the school community can move into the new building; and if he will make a statement on the matter. [21731/17]

Photo of Jan O'SullivanJan O'Sullivan (Limerick City, Labour)
Link to this: Individually | In context | Oireachtas source

205. To ask the Minister for Education and Skills the position regarding the construction of a new school (details supplied); when he expects the school community to be able to move into the new building; and if he will make a statement on the matter. [21734/17]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 204 and 205 together. The schools referred to by the Deputy are currently under construction and the projects are due to be completed by the end of July 2017. The new school buildings will be handed over immediately following completion. 