Schools Building Projects Status

Photo of Mick WallaceMick Wallace (Wexford, Independent)
Link to this: Individually | In context | Oireachtas source

244. To ask the Minister for Education and Skills the length of time a school building project (details supplied) has been at stage 2B, detailed design; the average time a new school construction project spends at stage 2B; the cause of the delay in this project build; when he envisages construction will be begin on this project; and if he will make a statement on the matter. [12850/17]

Photo of Mick WallaceMick Wallace (Wexford, Independent)
Link to this: Individually | In context | Oireachtas source

245. To ask the Minister for Education and Skills the name of the architect on a school building project (details supplied); the amount being spent on the architectural process; if the spend on architectural services for this project will run over the initial budget; if so, the amount by which it will run over; the justification for any overspend; and if he will make a statement on the matter. [12851/17]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 244 and 245 together.

The major building project to which the Deputy refers was authorised to progress to Stage 2b (Detailed design) in December 2014. The project is now close to completing stage 2(b).

In general, it would be expected that a project would progress through stage 2(b) in about 7 to 12 months although some can take longer depending on the complexities of the particular project.

It is envisaged that the project will be progressed to tender stage in the coming months with a view to commencing on site before the end of 2017.

The architectural services on this project are being provided from my Departments internal architectural staffing resources. The other design team members are external consultants appointed following a public tender exercise.

The total amount paid to date on Design Team fees to date is €108,815 (excluding Vat). These payments do not include the cost of architectural services as these are being provided directly by the Department. There is no initial budget in respect of the architectural services element for this project and therefore the question of a budget overrun for architectural services does not arise.

The Stage 2(b) (Detailed Design) documents are currently been finalised by the design team for submission to my Department. Once the submission is received and reviewed by my Department my officials will revert to the school with regard to the further progression of the project in line with the intended timeframe outlined above.