Schools Building Projects Expenditure

Photo of Brendan GriffinBrendan Griffin (Kerry, Fine Gael)
Link to this: Individually | In context | Oireachtas source

284. To ask the Minister for Education and Skills his views on a matter (details supplied) regarding a school in County Kerry. [9591/17]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

My Department fully funded the provision of a new 12 classroom building for the school to which the Deputy refers. In this regard it paid the Design Team fees, construction costs and all other ancillary costs.

The costs incurred by the school do not relate to the project actually delivered and they were incurred by the school without approval from the Department. Accordingly, the Department will not be meeting them.

The school has been informed that to qualify for Exchequer funding, it is a fundamental principle to have prior approval from the Department. Schools that incur costs without such approval must meet those costs themselves.