Written answers

Tuesday, 27 September 2016

Department of Education and Skills

Schools Building Projects Status

Photo of Brendan  RyanBrendan Ryan (Dublin Fingal, Labour)
Link to this: Individually | In context | Oireachtas source

251. To ask the Minister for Education and Skills the reason for the delay in building phase 2 of a college (details supplied); when building works are due to commence; and his views on whether phase 1 is not fit for purpose; and if he will make a statement on the matter. [26744/16]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The building project referred to by the Deputy is at an advanced stage of architectural planning Stage 2(b) - Detailed Design, which involves planning permission, fire certificate and disability access certificate and the completion of tender documents. All statutory approvals have been secured.

Phase 1 of the school was completed in 2013 and the school authority has given my Department no indication that it considers the building be anything other than "fit for purpose".

The second phase of the project provides for a new build to cater for an additional 650 pupils, a Special Needs Unit, a PE Hall with fitness suite and changing facilities and ancillary accommodation including a school library.

The Stage 2(b) report was recently submitted to my Department for review. Once the review is completed my Department will revert to the Design Team and ETB with regard to further progression of the project.

Comments

No comments

Log in or join to post a public comment.