Primary Care Centres Provision

Photo of Billy KelleherBilly Kelleher (Cork North Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

355. To ask the Minister for Health to provide in tabular form the primary care centre projects announced on 17 July 2012; the current status of same; and if he will make a statement on the matter. [23312/16]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Programme for a Partnership Government sets out a clear vision for our health services which is community based and responsive and accessible to patients. Supporting infrastructure, procured through a combination of public and private investment, will facilitate the delivery of multi-disciplinary primary health care. However, while the Government's objective is to deliver a high quality, integrated and cost effective health care service the mechanism and timescale for delivery of primary care centres is dependent on a number of factors. Regardless of the delivery mechanism, all potential primary care infrastructure is subject to suitable locations being offered / provided / available, to successful planning processes and GP commitment to sharing accommodation and delivering health care services with HSE staff. In addition the operational lease mechanism is subject to market pressures such as the developers' access to adequate financing. Some of these factors are outside the control of the Health Service Executive. Delivery of primary care infrastructure is a dynamic process, constantly evolving to take account of changing circumstances including the feasibility of implementation. The current status of the projects is set out in the following table.

Primary Care CentresJuly 2012 - 35 locationsPQ 23312/16

answer 20/07/2016
Project Status
CountyHSE RegionCountyLocation/PCT NameDelivery MechanismQ2 2016 -30 June 2016
1DMLDublin Rowlagh/North ClondalkinDirect buildStage 2a design team report now complete.  HSE finalising purchase agreement of site at Collinstown Park School. Purchase agreement is subject to planning permission being granted for the development.  
2DMLDublin Crumlin/DrimnaghDirect buildPlanning not completed in timeframe for PPP.
3DMLDublin Knocklyon/RathfarnhamDirect buildPlanning not completed in timeframe for PPP.
4DMLWicklowRathdrum Operational LeasePlanning approved.  HSE has finalised layouts.  Construction due to commence end Sept 2016, with projected 13 month construction programme. Projected operational Q4 2017.
5DMLKildareKilcockPPPConstruction underway - front entrance works and foundations.
6DNEDublin Coolock/DarndalePPPConstruction underway - demolition works.
7DNEDublin Summerhill, north inner city DublinPPPConstruction underway - service diversion works.
8DNEDublin BalbrigganOperational LeaseConstruction underway and completion projected Q4 2016. Projected operational Q1 2017.
9DNEDublin SwordsOperational LeasePreferred site sold. New advertisement required.
10DNELouthDrogheda northOperational LeaseDeveloper re-engaged. Progressing to legal discussions.
11DNEMeathLaytown and BettystownOperational LeaseDiscussion underway with new owners.
12DNEMeathKellsOperational LeaseOperational Q1 2016
13DNEMonaghanCarrickmacrossNov 2014 advertisement for operational lease mechanism delivery.

No expressions of interest received.
Viable expression of interest received recently. Formal submissions submission awaited.
14SouthCarlowTullow/Rathvilly/HacketstownDirect buildAdjoining landowner has re-engaged with HSE. Options being reviewed.
15SouthKilkennyKilkenny cityNov 2014 advertisement for operational lease mechanism delivery - suitable for further considerationPriced offer received. Letter of Intent issued.
16SouthWexfordWexford townPPPConstruction underway - site works and demolition works.
17SouthWaterfordDungarvanPPPConstruction underway - preparing foundations.
18SouthWaterfordWaterford cityPPPConstruction underway - bulk excavation and piling works.
19SouthCorkCork city - TogherNov 2014 advertisement for operational lease mechanism delivery - suitable for further considerationHSE reviewing stage 2 submissions. Stage 3 projected to proceed Q3 2016
20SouthKerryTraleeOperational LeaseRe-advertised. Stage 2 review complete; stage 3 documentation being issued.
21SouthTipperaryCarrick-on-SuirPPPConstruction underway - site works and piling works.
22SouthTipperaryClonmelNov 2014 advertisement for operational lease mechanism delivery - suitable for further considerationStage 2 submissions being reviewed. Stage 3 projected to proceed in Q3 2016.
23WestTipperaryThurlesNov 2014 advertisement for operational lease mechanism delivery - suitable for further considerationLetter of Intent issued 10/12/2015. Project progressing toward Agreement for Lease.
24WestLimerickLimerick city (Ballinacurra/Weston)PPPConstruction underway - preparing foundations.
25WestClareEnnisNov 2014 advertisement for operational lease mechanism delivery. Re-advertisement to be considered.
26WestGalway TuamPPPConstruction underway - preparing foundations.
27WestGalway GortNov 2014 advertisement for operational lease mechanism delivery.Letter of Intent withdrawn 24/05/2016. Possible re-advertisement.
28WestRoscommonBoylePPPConstruction underway - preparing foundations.
29WestRoscommonBallaghadereenNov 2014 advertisement for operational lease mechanism delivery - suitable for further considerationLetter of Intent issued 27/10/2015. Progressing to Agreement for Lease.
30WestMayoWestportPPPConstruction underway - site works.
31WestMayoClaremorrisPPPConstruction underway - preparing foundations.
32WestSligoBallymotePPPConstruction underway - earthworks underway.
33WestDonegalDungloeDirect buildExtension to existing building. Absence of GP interest
34WestDonegalDonegal townOperational LeaseRe-advertisement required.

In July 2012, Coolock and Darndale were announced as two separate locations but are being delivered as one location.