Written answers

Tuesday, 5 July 2016

Department of Communications, Energy and Natural Resources

Electricity Transmission Network

Photo of Seán FlemingSeán Fleming (Laois, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

628. To ask the Minister for Communications, Energy and Natural Resources his role relating to compliance or non-compliance with the strategic environmental impact assessment regarding Gate 3 decisions; and if he will make a statement on the matter. [19652/16]

Photo of Denis NaughtenDenis Naughten (Roscommon-Galway, Independent)
Link to this: Individually | In context | Oireachtas source

The regulation of the electricity network is a matter for the Commission for Energy Regulation (CER) which is an independent statutory body and I have no function in the matter.

The Gate process, including the Gate 3 process, is an administrative grid connection process managed by the CER in accordance with its regulatory functions.  I am informed by the CER that a Strategic Environmental Assessment was not required in regard to Gate 3. However, as is the case with all Directions issued by the  CER, the Gate 3 Direction was subject to public consultation before being finalised in December 2008.

Comments

No comments

Log in or join to post a public comment.