175. To ask the Minister for Defence the funding he allocated and the funding spent on capital projects and other initiatives in the constituency of Louth East Meath, by project and initiative, by completion date and by cost, for the past five years; and if he will make a statement on the matter. [3558/16]

Photo of Simon CoveneySimon Coveney (Cork South Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Department is engaged in an ongoing building programme designed to modernise and enhance the training, operational and accommodation facilities available to members of the Defence Forces.

Projects for completion under the programme are identified on an ongoing basis by the military and these projects are prioritised for inclusion as part of the annual programme.

The capital element of the programme focuses mainly on infrastructural projects comprising the construction of new buildings and the refurbishment of existing buildings and facilities. The cost of design team services required in order to complete these projects are also charged to the capital building programme.

The following table shows the cost of projects committed to in the constituency of Louth East Meath under the Department’s capital building programme in each of the years 2011 to 2015.

Works Commenced Project Cost to date
2011 Dundalk - Locker Block refurbishment € 920,567

2012 Nil -
2013 Gormanston - Officers Mess heating system upgrade € 76,054

2013 Dundalk - CCTV upgrade € 107,133

2014 Nil -
2015 Gormanston – Upgrade of Sewage Treatment Plant to provide tertiary treatment *

€ 81,720

*Project not yet complete

In addition to the major capital projects as outlined above, there are ongoing works required to ensure the upkeep and repair of buildings and provide facilities generally for personnel. These works are charged as current expenditure under the programme.  The main works which were committed to over the above period were as follows.

Works Commenced Project Cost to date
2011 Nil -
2012 Dundalk - Officers' Mess, Gate Bldg & Boiler house - reroof € 53,646
2012 Dundalk - Ration Stores, walkway repair € 28,665
2012 Dundalk - Roads and squares resurfacing € 101,455
2013 Dundalk - Billet block upgrade € 321,592
2013 Gormanston - repairs to waste water plant* € 20,430
2014 Nil -
2015 2 Bde - Redbarns Range - sundry resurfacing* € 66,567
*Project not yet complete