Written answers
Tuesday, 15 December 2015
Department of Public Expenditure and Reform
Flood Relief Schemes Status
Seán Fleming (Laois-Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
181. To ask the Minister for Public Expenditure and Reform the status of all flood relief schemes in County Cork at planning, construction and post-construction phase, the commencement and completion dates for each scheme, the funding envisaged for all such schemes and the annual funding for such schemes in the years 2011 to 2015, in tabular form; and if he will make a statement on the matter. [45201/15]
Seán Fleming (Laois-Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
182. To ask the Minister for Public Expenditure and Reform the status of all flood relief schemes in County Kerry at planning, construction and post-construction phase, the commencement and completion dates for each scheme, the funding envisaged for all such schemes and the annual funding for such schemes in the years 2011 to 2015, in tabular form; and if he will make a statement on the matter. [45202/15]
Seán Fleming (Laois-Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
183. To ask the Minister for Public Expenditure and Reform the status of all flood relief schemes in County Clare at planning, construction and post construction phase, the commencement and completion dates for each scheme, the funding envisaged for all such schemes and the annual funding for such schemes in the years 2011 to 2015 in tabular form; and if he will make a statement on the matter. [45203/15]
Seán Fleming (Laois-Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
184. To ask the Minister for Public Expenditure and Reform if he will provide an update with regard to all flood relief schemes in County Tipperary at planning, construction and post construction phase; the commencement and completion dates for each scheme; if he will provide in tabular form a breakdown of funding envisaged for all such schemes, as well as the annual funding for such schemes over the 2011-2015 period; and if he will make a statement on the matter. [45204/15]
Seán Fleming (Laois-Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
185. To ask the Minister for Public Expenditure and Reform the status of all flood relief schemes in County Waterford at planning, construction and post construction phase, the commencement and completion dates for each scheme, the funding envisaged for all such schemes and the annual funding for such schemes in the years 2011 to 2015 in tabular form; and if he will make a statement on the matter. [45205/15]
Seán Fleming (Laois-Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
186. To ask the Minister for Public Expenditure and Reform the status of all flood relief schemes in County Limerick at planning, construction and post construction phase, the commencement and completion dates for each scheme, the funding envisaged for all such schemes and the annual funding for such schemes in the years 2011 to 2015 in tabular form; and if he will make a statement on the matter. [45206/15]
Simon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source
I propose to take Questions Nos. 181 to 186, inclusive, together.
The following table sets out the details for all major flood relief schemes in the counties indicated at planning, construction and post construction phase, the period of construction, a breakdown of the annual funding for such schemes over the 2011–2015 period.
Scheme | Stage | Period of Construction | Cost €000 2011 | Cost €000 2012 | Cost €000 2013 | Cost €000 2014 | Cost €000 2015 * |
---|---|---|---|---|---|---|---|
Co Cork | |||||||
Mallow North | Construction completed | 2008 - 2010 | 472 | 285 | 400 | 211 | 24 |
Mallow South & West | Construction completed | 2011 - 2014 | 4185 | 3108 | 987 | 609 | 837 |
Fermoy North | Construction completed | 2009 -2011 | 1021 | 537 | 1015 | 250 | 79 |
Fermoy South | Construction completed | 2012 - 2015 | 193 | 5315 | 8748 | 4190 | 347 |
Bandon | Tender/Confirmation** | Expected 2016-2018 | 187 | 114 | 562 | 441 | 197 |
Skibbereen | Confirmation** | Expected 2016-2018 | - | 8 | 321 | - | 310 |
Lower Lee (Cork City) | Design | Expected 2017 - 2021 | |||||
Blackpool | Design/Public Exhibition | Expected 2017 - 2019 | 6 | 0 | 93 | 478 | 296 |
Glashaboy (Glanmire) | Design | Expected 2017 - 2018 | - | - | - | 90 | - |
Douglas/Togher | Design | Expected 2017 - 2018 | - | - | - | 146 | - |
Crookstown | Design | Expected 2017 - 2018 | - | - | - | - | - |
Ballymakeera | Design | Expected 2017 - 2018 | 5 | 11 | 41 | 3 | - |
Clonakilty | Detailed Design following Public Exhibition | Expected 2017 - 2018 | - | - | 3 | 163 | 319 |
Midleton | Appointment of consultants | Expected 2017 - 2018 | - | - | - | - | - |
County Kerry | N/a | N/a | N/a | N/a | N/a | N/a | N/a |
County Clare | |||||||
Ennis Upper | Construction Completed | 2008-2010 | 2,222 | 5 | - | - | - |
Ennis Lower | Construction Substantially complete | 2013-2015 | 169 | 94 | 9,659 | 4,074 | 765 |
Ennis South | Design | Expected 2016-2018 | - | 187 | - | - | 116 |
County Tipperary | |||||||
Templemore | Confirmation** | Expected 2016-2018 | - | 40 | - | 125 | 47 |
Clonmel West | Complete | 2008 – 2010 2014 (separate phase) | 3,419 | 539 | 331 | 1,077 | 178 |
Clonmel North & East | Complete | 2010 - 2012 | 7,856 | 3,590 | 455 | 121 | 41 |
County Waterford | |||||||
Waterford City Phase 1 | Complete | 2009-2010 | 600 | 63 | - | - | - |
Waterford City Phases 2,3,4 | Substantially complete | 2012-2015 | - | 3,120 | 3,851 | 4240 | 2108 |
County Limerick | |||||||
King's Island Limerick City | Design/Environmental Screening and Assessment | Too early to be specific but possible construction in late 2017/early 2018; construction expected to take 18/24 months | - | - | - | 691 | - |
Foynes | About to appoint Contractor | Estimated - Summer 2016 | - | - | - | 36 | - |
** Confirmation = Approval under Arterial Drainage Acts by Minister for Public Expenditure and Reform
The expected construction periods indicated are based on current best estimates having regard to the fact that many schemes are at a very early stage.
In relation to the funding of schemes, the Government has provided a total capital allocation of €430 million for flood risk management over the years 2016-2021 and this will be sufficient to meet the funding requirements of all the above indicated scheme yet to commence construction.
In addition to the above major schemes, the local authorities for the counties concerned may have carried out more localised minor flood relief works either using their own funding or with funding provided through the Office of Public Works Minor Flood Mitigation and Coastal Protection Scheme.