174. To ask the Minister for Public Expenditure and Reform the flood relief schemes in County Cork at planning, construction and post-construction phases, the commencement and completion dates for each scheme, the funding envisaged for all such schemes, and the funding for such schemes in the years 2011 to 2015 in tabular form; and if he will make a statement on the matter. [44841/15]
Simon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source
The table sets out the details for all major flood relief schemes in County Cork at planning, construction and post-construction phase, the period of construction, a breakdown of the annual funding for such schemes over the 2011-2015 period.
Scheme | Stage | Period of Construction | Cost €000 2011 | Cost €000 2012 | Cost €000 2013 | Cost €000 2014 | Cost €000 2015 * |
---|---|---|---|---|---|---|---|
Co Cork | |||||||
Mallow North | Construction completed | 2008 - 2010 | 472 | 285 | 400 | 211 | 24 |
Mallow South & West | Construction completed | 2011 - 2014 | 4185 | 3108 | 987 | 609 | 837 |
Fermoy North | Construction completed | 2009 -2011 | 1021 | 537 | 1015 | 250 | 79 |
Fermoy South | Construction completed | 2012 - 2015 | 193 | 5315 | 8748 | 4190 | 347 |
Bandon | Tender/Confirmation** | Expected 2016-2018 | 187 | 114 | 562 | 441 | 197 |
Skibbereen | Confirmation** | Expected 2016-2018 | - | 8 | 321 | - | 310 |
Lower Lee (Cork City) | Design | Expected 2017 - 2021 | |||||
Blackpool | Design/Public Exhibition | Expected 2017 - 2019 | 6 | 0 | 93 | 478 | 296 |
Glashaboy (Glanmire) | Design | Expected 2017 - 2018 | - | - | - | 90 | - |
Douglas/Togher | Design | Expected 2017 - 2018 | - | - | - | 146 | - |
Crookstown | Design | Expected 2017 - 2018 | - | - | - | - | - |
Ballymakeera | Design | Expected 2017 - 2018 | 5 | 11 | 41 | 3 | - |
Clonakilty | Detailed Design following Public Exhibition | Expected 2017 - 2018 | - | - | 3 | 163 | 319 |
Midleton | Appointment of consultants | Expected 2017 - 2018 | - | - | - | - | - |
**Confirmation = Approval under Arterial Drainage Acts by Minister for Public Expenditure and Reform
The expected construction periods indicated are based on current best estimates having regard to the fact that many schemes are at a very early stage.
In relation to the funding of schemes, the Government has provided a total capital allocation of €430 million for flood risk management over the years 2016-2021 and this will be sufficient to meet the funding requirements of all the above indicated scheme yet to commence construction.
In addition to the above major schemes, Cork city and county councils have carried out more localised minor flood relief works either using their own funding or with funding provided through the Office of Public Works Minor Flood Mitigation and Coastal Protection Scheme.