Written answers

Tuesday, 15 December 2015

Department of Public Expenditure and Reform

Flood Relief Schemes Status

Photo of Michael MoynihanMichael Moynihan (Cork North West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

174. To ask the Minister for Public Expenditure and Reform the flood relief schemes in County Cork at planning, construction and post-construction phases, the commencement and completion dates for each scheme, the funding envisaged for all such schemes, and the funding for such schemes in the years 2011 to 2015 in tabular form; and if he will make a statement on the matter. [44841/15]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The table sets out the details for all major flood relief schemes in County Cork at planning, construction and post-construction phase, the period of construction, a breakdown of the annual funding for such schemes over the 2011-2015 period.

SchemeStagePeriod of ConstructionCost €000 2011Cost €000 2012Cost €000 2013Cost €000 2014Cost €000 2015 *
Co Cork
Mallow NorthConstruction completed2008 - 201047228540021124
Mallow South & WestConstruction completed2011 - 201441853108987609837
Fermoy NorthConstruction completed2009 -20111021537101525079
Fermoy SouthConstruction completed2012 - 2015193

5315


8748


4190


347
BandonTender/Confirmation**Expected 2016-2018

187


114


562


441


197
SkibbereenConfirmation**Expected 2016-2018

-


8


321


-


310
Lower Lee (Cork City)DesignExpected 2017 - 2021
BlackpoolDesign/Public ExhibitionExpected 2017 - 2019

6


0


93


478


296
Glashaboy (Glanmire)DesignExpected 2017 - 2018

-


-


-


90


-
Douglas/TogherDesignExpected 2017 - 2018

-


-


-


146


-
CrookstownDesignExpected 2017 - 2018

-


-


-


-


-
BallymakeeraDesignExpected 2017 - 2018511413-
ClonakiltyDetailed Design following Public ExhibitionExpected 2017 - 2018

-


-
3163319
MidletonAppointment of consultantsExpected 2017 - 2018

-


-


-


-


-
*Expenditure to end November 2015

**Confirmation = Approval under Arterial Drainage Acts by Minister for Public Expenditure and Reform

The expected construction periods indicated are based on current best estimates having regard to the fact that many schemes are at a very early stage.

In relation to the funding of schemes, the Government has provided a total capital allocation of €430 million for flood risk management over the years 2016-2021 and this will be sufficient to meet the funding requirements of all the above indicated scheme yet to commence construction.

In addition to the above major schemes, Cork city and county councils have carried out more localised minor flood relief works either using their own funding or with funding provided through the Office of Public Works Minor Flood Mitigation and Coastal Protection Scheme.