Written answers

Tuesday, 8 December 2015

Department of Public Expenditure and Reform

Flood Prevention Measures

Photo of Pat BreenPat Breen (Clare, Fine Gael)
Link to this: Individually | In context | Oireachtas source

190. To ask the Minister for Public Expenditure and Reform the status of a project (details supplied) in County Clare; and if he will make a statement on the matter. [44070/15]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Office of Public Works (OPW) very recently received from Clare County Council (CCC) a copy of the feasibility study report prepared by the engineering consultants engaged by CCC to examine the flooding issues at the location mentioned. The OPW will be responding to CCC in due course when it has completed a full review of the feasibility study report.

Photo of Bernard DurkanBernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

191. To ask the Minister for Public Expenditure and Reform if and when the necessary funding will be approved for drainage and flood prevention works associated with the Morrell River in County Kildare; and if he will make a statement on the matter. [44084/15]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Kildare County Council (KCC), in consultation with the Office of Public Works (OPW), engaged Consulting Engineers to carry out a Full Feasibility Study, Cost Benefit Analysis (CBA), and Environmental Impact Statement (EIS) on the Lower Morrell River and the surrounding River Catchment in an effort to resolve the outstanding localised flooding issues in the Straffan area. A Steering Group which comprises representatives of KCC, OPW and the consultants, was set up to advance the project.

KCC and their consultants submitted a Draft Options Report/Feasibility Study to OPW outlining possible flood relief measures for the Lower Morrell River Catchment in 2014. Following consideration of the draft report by the OPW, it was agreed by the Steering Group that the consultants would carry out a more detailed review of the proposed scheme with further analysis of the various options considered to assess the benefits of the current works proposals as they have evolved. The review would also investigate if there are additional or alternative and more cost effective measures that can be put in place to alleviate flooding in the area. Any changes identified by the review process would need to be incorporated into the Cost Benefit Analysis and Environmental Impact Statement before the scheme can be advanced.

I am advised by my Officials that the consultants have completed the review process and KCC has submitted their findings to the OPW for consideration. It is envisaged that OPW and KCC will meet early in 2016 with a view to finalising the Feasibility Report. Once the Feasibility Report has been finalised, and provided the scheme is still economically and environmentally viable, KCC and the OPW will decide on how best to advance the proposed works. The OPW has included provision for the cost of the proposed works in its financial profiles in the period up to 2018.