Wind Energy Guidelines

Photo of Anthony LawlorAnthony Lawlor (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

534. To ask the Minister for Environment, Community and Local Government when the revised planning guidelines for wind development will be published; the reason for the excessive delay; if he will commit to the publication of the revised guidelines before the summer recess; and if he will make a statement on the matter. [27121/15]

Photo of Finian McGrathFinian McGrath (Dublin North Central, Independent)
Link to this: Individually | In context | Oireachtas source

538. To ask the Minister for Environment, Community and Local Government if he will provide a timeframe for issuing planning guidelines in respect of wind farms; the current stage of the process; and if he will make a statement on the matter. [27232/15]

Photo of Alan KellyAlan Kelly (Tipperary North, Labour)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 534 and 538 together.

In December 2013, my Department published proposed "draft" revisions to the noise, setbacks and shadow flicker aspects of the 2006 Wind Energy Development Guidelines. These draft revisions proposed the setting of a more stringent day and night noise limit of 40 decibels for future wind energy developments; a mandatory minimum setback distance of 500 metres between a wind turbine and the nearest dwelling for amenity considerations; and the complete elimination of shadow flicker between wind turbines and neighbouring dwellings.

A public consultation process was initiated on these proposed draft revisions to the Guidelines, which ran until February 21 2014. My Department received submissions from 7,500 organisations and members of the public during this public consultation process. It is intended that the revisions to the 2006 Wind Energy Development Guidelines will be finalised as soon as possible. In this regard, account has to be taken of the extensive response to the public consultation in framing the final guidelines. Further work is also advancing to develop technical appendices to assist planning authorities with the practical application of the noise measurement aspects of the Wind Guidelines.

The revisions to the Wind Energy Development Guidelines 2006, when finalised, will be issued under Section 28 of the Planning and Development Act 2000, as amended. Planning authorities, and, where applicable, An Bord Pleanála must have regard to guidelines issued under Section 28 in the performance of their functions under the Planning Acts.