Department of Communications, Energy and Natural Resources

Corrib Gas Field

Photo of Thomas PringleThomas Pringle (Donegal South West, Independent)
Link to this: Individually | In context | Oireachtas source

1143. To ask the Minister for Communications, Energy and Natural Resources the projected start date for gas production from the Corrib field; and if he will make a statement on the matter. [22272/15]

Photo of Alex WhiteAlex White (Dublin South, Labour)
Link to this: Individually | In context | Oireachtas source

Completion of the Corrib gas field development works, by the developer, together with obtaining all of the necessary consents, are the principal factors that will determine the date for first gas. Construction and testing of the infrastructure is ongoing with first gas anticipated later this year.