Written answers

Tuesday, 24 March 2015

Department of Communications, Energy and Natural Resources

Electricity Transmission Network

Photo of Seán ConlanSeán Conlan (Cavan-Monaghan, Fine Gael)
Link to this: Individually | In context | Oireachtas source

932. To ask the Minister for Communications, Energy and Natural Resources if the Tobin report was within EirGrid's knowledge when the independent expert panel requested additional information regarding details of EirGrid's consideration of the suitability of public roads and disused railways lines for an underground cable route option; and if he will make a statement on the matter. [11146/15]

Photo of Alex WhiteAlex White (Dublin South, Labour)
Link to this: Individually | In context | Oireachtas source

An Independent Expert Panel was established in January 2014 to oversee the integrity of the process being undertaken by EirGrid to report on comprehensive, route-specific studies of overhead and underground options for both the Grid Link and Grid West projects.

While the North South Transmission Line project is outside of the Panel's Terms of Reference, the Panel agreed to provide an opinion on the compatibility of the methodologies to be employed on the Grid Link and Grid West projects with what had already been done on the North South project up to and including 2 May 2014, being the date that the Panel decided to examine the North-South project.

EirGrid submitted its report to the Panel in relation to the North South Project on 29 May 2014. The Panel subsequently sought additional supplementary information from EirGrid regarding various matters, including information relating to undergrounding options. EirGrid responded to this request for further information in an addendum to the original report on 19 June 2014. EirGrid was aware of the Underground Route Options document that was being prepared by Tobin Consulting Engineers, and which was subsequently published in July 2014.

It should be noted that the Tobin report referred to in the Question relates specifically to the Grid West project and is one of several pieces of analysis undertaken at the request of the Panel. In other words, the Tobin report was undertaken within the methodologies being employed on the Grid West project in accordance with Terms of Reference set by the Panel.

I should also highlight that I am advised that transmission capacity in the region of 1,500 MW is required for the North South Project. This requires a much larger installation than the Grid West scheme. The extent of the installation required for the North South Project means that neither local nor regional roads and road verges would be sufficiently wide to accommodate the works.

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick, Fine Gael)
Link to this: Individually | In context | Oireachtas source

933. To ask the Minister for Communications, Energy and Natural Resources if Ireland is implementing the new European electrical grid codes, 2015 to 2018, differently from other European Union Member States; if he will provide a rationale for that difference; and if he will make a statement on the matter. [11197/15]

Photo of Alex WhiteAlex White (Dublin South, Labour)
Link to this: Individually | In context | Oireachtas source

The internal energy market is a key policy goal for the European Union and its Member States. The delivery of the internal energy market is crucial to achieving the key goals of energy policy - energy security, competitiveness and environmental sustainability. The methodology for harmonisation and integration of cross border electricity markets is set out in the 2009 "Third Energy Package" - a package of EU Regulations and Directives. Significant progress with the implementation of the package has been achieved. Some of the detailed rules are still being developed and negotiated through the development of network codes and guidelines, particularly with regard to the European electricity markets.

Ireland is not implementing the codes and guidelines differently from other Member States. The network codes and guidelines, once agreed by Member States and the European Commission, will become legally binding European Regulations.

There are significant differences between the all-island wholesale electricity market and other European wholesale markets. Consequently, Ireland and Northern Ireland have secured an extension to the deadline for the implementation of one of the guidelines, the Capacity Allocation and Congestion Management (CACM) Guideline. Ireland must be compliant with all aspects of CACM by 31 December 2017, whereas other Member States will introduce the provisions of this guideline after it comes into force, expected later in 2015.

Comments

No comments

Log in or join to post a public comment.