217. To ask the Minister for Public Expenditure and Reform if he will provide details of all consultancy firms engaged by his Department during 2014; if he will also provide details of all the relevant fees paid to those firms during the period; and if he will make a statement on the matter. [1672/15]

Photo of Brendan HowlinBrendan Howlin (Wexford, Labour)
Link to this: Individually | In context | Oireachtas source

In response to the Deputy's question the following table outlines the total amount spent on consultancy firms engaged by my Department in 2014:

Name of External ReportCostsDate or Expected Date of PublicationName of External Consultant
Open Data project:

- Best Practice Handbook

- Data Audit Report

- Roadmap for Open Data

- Evaluation Framework

- Open Data Publication Handbook
€19,188.00July 2014Insight Centre for Data Analytics, NUI Galway
Development of Training & Organisation Development€22,900July 2014



(date is approximate, relates to draft Report)
Baker Tilly Ryan Glennon.



Trinity House, Charleston Road, Ranelagh, Dublin 6
Value for Money Report of Dublin Castle's Conference Facilities€4,674.00 Incl Vat.Qtr 3, 2014Newmarket Consulting
Fund Structuring Services Agreement for Social Housing and Energy Efficiency in Ireland€26,766.655 November 2014European Investment Bank
Baseline Report Single Pension Scheme€24,9009 December 2014Mr Seamus O'Dwyer
Comparative Report on European  National Identification Numbers€37,500Publication pending the completion of the work of the PPSN review GroupHans Graux of time.lex CVBA, Brussels, Belgium
In the course of its normal business activity, the Office of Public Works engages technical consultants on many of its projects, primarily architectural and engineering.  The costs of these consultants would be included in the overall project costs and are not included here.