Written answers

Wednesday, 14 January 2015

Department of Education and Skills

Schools Building Projects Status

Photo of Éamon Ó CuívÉamon Ó Cuív (Galway West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

844. To ask the Minister for Education and Skills the progress regarding the replacement of the current school building of a school (details supplied) in County Galway with a new building; when work will commence on this building in 2015; and if she will make a statement on the matter. [1565/15]

Photo of Jan O'SullivanJan O'Sullivan (Limerick City, Labour)
Link to this: Individually | In context | Oireachtas source

The tenders for the project to which the Deputy refers have been assessed and the Design Team have sought clarifications from the lowest priced tenderer. On receipt of those clarifications my Department will continue to keep the school authority informed as the process progresses.

Photo of Éamon Ó CuívÉamon Ó Cuív (Galway West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

845. To ask the Minister for Education and Skills the progress made to date in providing a replacement building in respect of a school (details supplied) in County Galway in view of the very poor state of the current building; and if she will make a statement on the matter. [1567/15]

Photo of Jan O'SullivanJan O'Sullivan (Limerick City, Labour)
Link to this: Individually | In context | Oireachtas source

I can confirm to the Deputy that the schools in question submitted major capital applications for extension and refurbishment to my Department.

My Department has been liaising with the school authorities regarding the schools long term projected enrolments (LTPE) and a revised LTPE for each school has recently been agreed. The Schedules of Accommodation have also recently been finalised.

In that regard a site visit to the schools in question was undertaken at the end of 2014. Once the site visit report has been finalised the projects concerned will be considered for progression into the architectural planning process.

As the Deputy will understand, due to the competing demands on my Department's capital budget imposed by the need to prioritise the limited funding available for the provision of essential additional school accommodation to meet increasing demographic requirements, it is not possible at this point to provide an indicative timeframe for the provision of an extension to the schools in question.