Written answers

Tuesday, 15 July 2014

Department of Education and Skills

Schools Building Projects Status

Photo of Kevin HumphreysKevin Humphreys (Dublin South East, Labour)
Link to this: Individually | In context | Oireachtas source

284. To ask the Minister for Education and Skills if she will provide an update on the plans for a new school building for a school (details supplied); when will it move off site; if a temporary location been found while construction takes place; when the project is expected to be finished; and if she will make a statement on the matter. [30994/14]

Photo of Jan O'SullivanJan O'Sullivan (Limerick City, Labour)
Link to this: Individually | In context | Oireachtas source

Responsibility for the delivery of a new 16 classroom school referred to by the Deputy has been devolved to the Office of Public Works.

The project is at the early stages of architectural planning and is one of the school projects approved to proceed to construction in 2014/2015. My Department officials are currently assessing options in relation to off-site accommodation that will be required to facilitate the delivery of the school.

When construction will commence will be dependent on the progress of the project through the various stages of design and the local authority planning process.

Comments

No comments

Log in or join to post a public comment.