Written answers

Tuesday, 28 January 2014

Department of Environment, Community and Local Government

Water and Sewerage Schemes Status

Photo of Jim DalyJim Daly (Cork South West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

545. To ask the Minister for Environment, Community and Local Government if he will confirm the plans of Irish Water including the projected timelines for commencement and completion for the construction of a new main drainage scheme in Bandon, County Cork. [3948/14]

Photo of Michael McCarthyMichael McCarthy (Cork South West, Labour)
Link to this: Individually | In context | Oireachtas source

552. To ask the Minister for Environment, Community and Local Government if he will provide an update on the progress of a scheme (details supplied); if he will further provide assurances that this scheme will proceed as planned; if the funding that was approved for this project is still in place; and if he will make a statement on the matter. [4134/14]

Photo of Noel HarringtonNoel Harrington (Cork South West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

555. To ask the Minister for Environment, Community and Local Government if he has addressed the concerns of Bandon Town Council in their letter to him dated 28 November 2013 (details supplied); if these works will proceed as planned during 2014; if funding is still in place to complete the project; and if he will make a statement on the matter. [4150/14]

Photo of Phil HoganPhil Hogan (Carlow-Kilkenny, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 545, 552 and 555 together.

Contracts for both a wastewater treatment plant upgrade, and network for the Bandon Sewerage Scheme, Phase 2, were included in my Department’s Water Services Investment Programme 2010 – 2013 among the contracts to start during that period.

In February 2012 I approved funding of €3.9 m for the network contract on the scheme; Cork County Council awarded the contract in March 2012 and the Contractor commenced work at that time. However, contractual issues subsequently emerged and the Contractor and the Council agreed to the termination of the contract by mutual consent. Cork County Council has appointed a consultant to complete the Contract Documents which will incorporate all of the outstanding works on the network element of the scheme. In respect of the Wastewater Treatment Plant Upgrade, Cork County Council were to prepare a Preliminary Report for this element of the scheme.

However, prior to the transfer of responsibility for the delivery of water services capital infrastructure to Irish Water on 1 January 2014, the Council had not completed the Contract Documents for the Network Contract nor had they submitted a Preliminary Report for the Wastewater Treatment Plant Upgrade Contract. Irish Water is now responsible for the delivery of water services capital infrastructure. It is currently preparing a Capital Investment Plan for 2014 – 2016 that will provide for the transition of projects included in the 2010 - 2013 Water Services Investment Programme.

Comments

No comments

Log in or join to post a public comment.