253. To ask the Minister for Education and Skills the position regarding the school building programme in respect of a school (details supplied) in Dublin 13; and if he will make a statement on the matter. [1769/14]

Photo of Ruairi QuinnRuairi Quinn (Dublin South East, Labour)
Link to this: Individually | In context | Oireachtas source

I am pleased to advise the Deputy that a building project for the school to which he refers is currently at an early stage of the architectural planning process. Officials from my Department met with the school Patron's representatives recently regarding the progression of the project. The Patron and their Design Team are currently completing the Stage 2(a) report for submission to my Department. Following satisfactory completion of this report and subject to no issues arising, the project will be authorised to commence the application for statutory approvals, which includes the application for planning permission.

The projects included in the 2014 Construction Programme announced on 29th November last are scheduled to proceed to construction in 2014 and are part of the Five Year Plan launched in March 2012. School building projects, including the project referred to by the Deputy, which have not been included in the five year construction programme, but which were previously initiated will continue to be progressed to final planning stages in anticipation of the possibility of further funds being available to the Department in the future.

In the meantime, my Department approved funding to the school in February 2013 to provide two additional mainstream classrooms to cater for increasing enrolments. I understand that works are well advanced on site to provide this accommodation. I understand also that the school has recently submitted an application for further accommodation and that the application is currently being assessed. A decision will be conveyed to the school authority when the assessment process has been completed.

Photo of Finian McGrathFinian McGrath (Dublin North Central, Independent)
Link to this: Individually | In context | Oireachtas source

254. To ask the Minister for Education and Skills the position regarding the school building project in respect of a school (details supplied) in Dublin 3; and if he will make a statement on the matter. [1770/14]

Photo of Ruairi QuinnRuairi Quinn (Dublin South East, Labour)
Link to this: Individually | In context | Oireachtas source

The major building project for the school referred to by the Deputy is currently at an advanced stage of architectural planning - Stage 2b - Detailed Design. All statutory approvals have been obtained and the Design Team has recently been authorised to complete the Stage 2b report and submit it to my Department for review. Due to competing demands on the Department's capital budget imposed by the need to prioritise the limited funding available for the provision of additional school accommodation to meet increasing demographic requirements it was not possible to include this project in the 5 year construction programme announced in March 2012.

School building projects, including the project referred to by the Deputy, which were not included in the current five year construction programme will continue to be progressed to final planning stages in anticipation of the possibility of further funds being available to the Department in the future.