Schools Building Projects Status

Photo of Jonathan O'BrienJonathan O'Brien (Cork North Central, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

307. To ask the Minister for Education and Skills the funding available for phase two of a school (details supplied) in County Meath; when this phase of the school will be completed and ready for use; and if he will make a statement on the matter. [46358/13]

Photo of Ruairi QuinnRuairi Quinn (Dublin South East, Labour)
Link to this: Individually | In context | Oireachtas source

Phase 1 of a 1000 pupil second level school referred to by the Deputy proceeded to tender and construction in 2013. This phase of the project is currently on site and is nearing completion.

Phase 2 of the project is currently at an early stage of Architectural Planning - Stage 1 which is the initial sketch Design Stage. At this early stage of architectural planning it is not possible to provide an expected commencement or completion date for the construction of Phase 2. However, the provision of the full 1000 pupil school is encompassed within the 5 year construction programme as announced in March 2012.

Photo of Jonathan O'BrienJonathan O'Brien (Cork North Central, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

308. To ask the Minister for Education and Skills the date on which the gym in a school (details supplied) in County Meath will be signed off on by the Department; and if he will make a statement on the matter. [46359/13]

Photo of Ruairi QuinnRuairi Quinn (Dublin South East, Labour)
Link to this: Individually | In context | Oireachtas source

The General Purpose room in the school to which the Deputy refers has reached substantial completion and was handed over to the school on 1 November 2013.