156. To ask the Minister for Communications, Energy and Natural Resources the input his Department has had in the choosing of the areas where EirGrid are currently proposing to erect pylons within Ireland; if other options were considered, that is underground lines or lines at sea; the agreements that have been made between his Department and EirGrid; and if he will make a statement on the matter. [45475/13]

Photo of Pat RabbittePat Rabbitte (Dublin South West, Labour)
Link to this: Individually | In context | Oireachtas source

While several of the issues raised in the Question are matters for Eirgrid, and not ones in which I, as Minister, have any role or function, I will respond to the issues that fall within the ambit of my Department and Government policy in this area.

Neither the Government nor I seek to direct the energy infrastructure developers to particular sites or routes or technologies as was made clear in the July 2012 Government Policy Statement on the Strategic Importance of Transmission and Other Energy Infrastructure. That statement emphasises that these are matters for the developers and for the forward planning process through regional and local development plans and at project level through the development management process. In this context, energy infrastructure developers are encouraged to work with the forward planning processes at regional and local levels to set clear contexts for assessment of individual applications for planning consent and to facilitate as wide a degree of consensus as possible regarding how and where to meet grid development needs.

The Government, as detailed in the July 2012 Policy Statement, expects the companies in making their choices of project specific technologies and routing, as well as mitigation measures, to take account of all relevant national and international standards, to follow best practice and ensure value for money and be informed by detailed consultation at local level.

Photo of John HalliganJohn Halligan (Waterford, Independent)
Link to this: Individually | In context | Oireachtas source

157. To ask the Minister for Communications, Energy and Natural Resources his views on whether there may be a conflict of interest on the part of the consulting engineering company (details supplied) that Eirgrid has employed to advise them on the selection of what they call the least constrained corridor in view of the fact that this company has also been employed by Tipperary County Council and a decision there could greatly impact on any decision made in County Waterford; and if he will make a statement on the matter. [45476/13]

Photo of Pat RabbittePat Rabbitte (Dublin South West, Labour)
Link to this: Individually | In context | Oireachtas source

This is a matter for EirGrid and one in which I, as Minister, have no function.