Written answers

Tuesday, 15 October 2013

Department of Environment, Community and Local Government

Water and Sewerage Schemes Provision

Photo of Jim DalyJim Daly (Cork South West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

206. To ask the Minister for Environment, Community and Local Government if he will provide an update in relation to the construction of a new main drainage scheme at Bandon, County Cork, including commencement and completion dates; and if he will make a statement on the matter. [43282/13]

Photo of Phil HoganPhil Hogan (Carlow-Kilkenny, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Water Services Investment Programme 2010 - 2013 provides for the development of a comprehensive range of new water services infrastructure in County Cork. It includes contracts under construction and to commence to the value of some €230 million in the county during the period of the Programme.

Contracts for both a wastewater treatment plant upgrade and network for the Bandon Sewerage Scheme Phase 2 are included as contracts to start during the life of the Programme. My Department is awaiting the submission of a Preliminary Report for the Wastewater Treatment Plant Scheme/Contract.

In relation to the Bandon Sewerage Scheme Phase 2 Network Contract Cork County Council has appointed a consultant to complete the Contract Documents which will incorporate all of the outstanding works on the scheme.