Written answers

Tuesday, 8 October 2013

Department of Education and Skills

Schools Building Projects Status

Photo of Caoimhghín Ó CaoláinCaoimhghín Ó Caoláin (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

246. To ask the Minister for Education and Skills the position regarding the development of a new school (details supplied) in County Louth. [42424/13]

Photo of Ruairi QuinnRuairi Quinn (Dublin South East, Labour)
Link to this: Individually | In context | Oireachtas source

The major building project for the school referred to by the Deputy is at an advanced stage of architectural planning.

Planning Permission has been granted and applications for Fire Certification and Disability Access Certification (DAC) are ongoing. Once the necessary statutory approvals have been secured the design team will complete the preparation of tender documents and the pre-qualification of contractors for the project. The project will then proceed to tender stage.

Photo of Bernard DurkanBernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

250. To ask the Minister for Education and Skills the degree to which he expects the school building programme to advance in the coming year with particular reference to the total number of new school places likely to be provided at primary and secondary level; and if he will make a statement on the matter. [42448/13]

Photo of Bernard DurkanBernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

257. To ask the Minister for Education and Skills the progress to date in respect of the school building programme, at primary and second level throughout County Kildare; the targets that have already been achieved and those outstanding; and if he will make a statement on the matter. [42455/13]

Photo of Bernard DurkanBernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

263. To ask the Minister for Education and Skills the extent to which the primary and second school building programme in County Kildare has advanced in each of the past three years to date with particular reference to the building of new schools, the replacement of existing school and his future plans regarding same; and if he will make a statement on the matter. [42461/13]

Photo of Ruairi QuinnRuairi Quinn (Dublin South East, Labour)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 250, 257 and 263 together.

The current status of all projects on the school building programme, including those for County Kildare, may be viewed on my Department's website at www.education.ie which is updated regularly throughout the year. The Deputy will be aware that the 5 year School Investment Plan announced in March 2012, provides for a €2 billion school capital investment programme, of which over €1.5 billion is being allocated to the funding of major school building projects, with the balance needed for the additional accommodation scheme, the prefab replacement initiative, the Emergency Works Scheme and the acquisition of sites. The Plan outlines the major school projects that are planned to proceed to construction over the duration of the Plan. The primary aim at the core of the Five Year Plan is focussed on meeting demographic demands to ensure that every child will have access to a physical school place and that our school system is in a position to cope with increasing pupil numbers. The plan will provide over 100,000 permanent school places, of which over 80,000 will be new school places.

Further to the Five Year Plan, my Department is committed to publishing a detailed annual programme in relation to individual major school projects commencing construction. In December 2011, details of 56 major school building projects to commence construction in 2012, the first year of the Plan, were published. In December 2012, details of 50 major school building projects were announced to commence construction in 2013, the second year of the Plan. Details of the building projects to commence construction in 2014 will be announced later on this year.

The Deputy will also be aware of the biggest initiative ever undertaken to reduce the reliance on rented prefabs in schools.. Under the Prefab Replacement initiative 2012 (Phase 1), my Department provided funding of in excess of €42 million for the replacement of over 458 prefab units in 170 schools with permanent accommodation. A further €15 million has been allocated under Phase II of the Prefab Replacement Initiative, that was announced in June this year, for the replacement of over 115 prefab units in 46 schools. This funding will be used to replace prefabs with permanent classroom and resource rooms accommodation. A total of eight schools in County Kildare will benefit from this initiative.

Also in June this year, the allocation of further funding as part of the Government's "investing in Infrastructure & Jobs" package, will enable a further 28 school projects to be progressed to construction. This investment will enable 18 primary schools, including a school in County Kildare, and 10 post-primary schools to be replaced or refurbished with state of the art classrooms and facilities for over 12,000 students. Details of all school capital works that have been funded by my Department may be viewed on my Department website and this is updated on a regular basis.

For the Deputy's convenience, a list of the major new schools/extension projects that were completed in County Kildare, between 2010 and to date in 2013 is outlined as follows.

Major school building projects in County Kildare completed from 2010 to date in 2013

YearSchool NameRoll No.Project
2013Scoil Phadraig, Ballylinan, Athy17064UNew 12 classroom school
2013SN Aine Naofa, Ard Cloc, Straffan17674BNew 16 classroom school + 4 special education tuition rooms
2013Scoil Bhride NS, Rathangan18018S12 classroom extension, ancillary accommodation and refurbishment works.
2012Sc Uí Fhiach, Maynooth20058T New 16 classroom school
2012Scoil Brid, Naas20114D8 classroom extension and 4 special education tuition rooms
2012Meánscoil Iognáid Ris, Naas61710CExtension/refurbishment
2011Scoil Phadraig Naofa, Athy16705ENew 26 classroom school
2011Scoil Bhride NS, Kill17662RNew 32 classroom school
2011Athy Model NS 06209JGeneral Purpose Room
2011Scoil Choca Naofa, Kilcock, 11976K11 classroom extension, G.P. room, ancillary accommodation and refurbishment of existing accommodation
2011Caragh NS, Naas18654A15 classroom extension, GP room and ancillary accommodation
2011Scoil Áth Í, Athy 20192AGeneral Purpose Room
2011Scoil na Naomh Uilig, Rickardstown, Newbridge (Phase II)20271T12 classroom extension
2010Scoil Bhride, Nurney16345ANew 8 classroom school
2010Scoil na Naomh Uilig, Rickardstown, Newbridge (Phase 1)20271TNew 16 classroom school
2010Presentation Convent, Maynooth00779U8 classroom extension
2010Scoil Bhride, Athgarvan13350B4 classroom extension, GP room & associated works
2010Athy Community College 70650LNew school, PE Hall & Autistic Unit