Link to this: Individually | In context | Oireachtas source

255. To ask the Minister for Public Expenditure and Reform the date on which it was formally accepted by the Office of Public Works that an area (details supplied) was returned to them in a satisfactory condition; and if he will make a statement on the matter. [20283/13]

Photo of Brendan HowlinBrendan Howlin (Wexford, Labour)
Link to this: Individually | In context | Oireachtas source

Due to adverse weather conditions, following the concerts in the Phoenix Park, works began in September 2012 and have been completed to our satisfaction. The State received €345,053 for the music concert series, which occupied the site for 3 weeks (approx).