Written answers

Tuesday, 4 December 2012

Department of Environment, Community and Local Government

Priory Hall Development

Photo of Tommy BroughanTommy Broughan (Dublin North East, Labour)
Link to this: Individually | In context | Oireachtas source

To ask the Minister for Environment, Community and Local Government if he will report on the Priory Hall, Dublin, resolution process; when he believes the resolution process will be concluded; and if he will make a statement on the matter. [54206/12]

Photo of Michael ColreavyMichael Colreavy (Sligo-North Leitrim, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

To ask the Minister for Environment, Community and Local Government if he will provide an update on the refurbishment and rebuild plans being considered for Prior Hall, Dublin; the reforms he will introduce to present recurrence of such a disaster including the end of self regulation; and if he will make a statement on the matter. [54249/12]

Photo of Phil HoganPhil Hogan (Carlow-Kilkenny, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 107 and 113 together.

The resolution process, which I understand is on-going, arose in the context of legal proceedings which were adjourned to afford relevant parties the opportunity to work together, under the chairmanship of Mr. Justice Finnegan (retired President of the High Court), to identify a way forward in relation to the complex problems at Priory Hall. Given that the matter is before the courts, it would be inappropriate for me to comment further other than to continue to urge all concerned to afford Mr. Justice Finnegan the opportunity to complete the task which he is undertaking.

In relation to the proposed Building Control reforms the position is that f following an extensive public consultation process undertaken earlier this year the Building Control (Amendment) Regulations 2012 are currently being finalised . The new regulations will provide, among other things, for the introduction of mandatory certificates of compliance by builders and designers of buildings confirming that the statutory requirements of the Building Regulations have been met in relation to the building concerned. Drawings and particulars demonstrating compliance must also be submitted to the local building control authority. In addition a building owner will be required to assign a registered professional to inspect the work during construction and also to certify that the completed building is in compliance with the requirements of the Building Regulations.

I believe that the measures outlined above are key steps necessary to strengthen the building control system and will be capable of delivering a stronger level of compliance with the requirements of the Building Regulations and a better quality of homes and buildings.