Schools Building Projects

Photo of Patrick NultyPatrick Nulty (Dublin West, Labour)
Link to this: Individually | In context | Oireachtas source

To ask the Minister for Education and Skills if the construction of new classrooms extension for a school (details supplied) in Dublin 15 is in his Departments capital works programme. [41830/12]

Photo of Ruairi QuinnRuairi Quinn (Dublin South East, Labour)
Link to this: Individually | In context | Oireachtas source

The major building project for the school referred to by the Deputy is not included in the 5 year construction programme. The project is at an early stage of architectural planning. Due to competing demands on the Department's capital budget imposed by the need to prioritise the limited funding available for the provision of additional school accommodation to meet increasing demographic requirements it was not possible to include this project in the 5 year construction programme announced in March. School building projects, including the project referred to by the Deputy, which have not been included in the five year construction programme, but which were announced for initial inclusion in the building programme will continue to be progressed to final planning stages in anticipation of the possibility of further funds being available to the Department in future years.

Photo of Patrick NultyPatrick Nulty (Dublin West, Labour)
Link to this: Individually | In context | Oireachtas source

To ask the Minister for Education and Skills if the permanent school building at a school (details supplied) in Dublin 15 will be ready for opening in September 2013. [41831/12]

Photo of Ruairi QuinnRuairi Quinn (Dublin South East, Labour)
Link to this: Individually | In context | Oireachtas source

Construction recently commenced on Phase 1 of school building project to which the Deputy refers. This phase will provide accommodation for circa 650 pupils. Subject to no issues arising, it is anticipated that this project will be completed in time for the start of the academic year 2013/14.

Photo of Patrick NultyPatrick Nulty (Dublin West, Labour)
Link to this: Individually | In context | Oireachtas source

To ask the Minister for Education and Skills when construction of a second level school at Tyrellstown in Dublin 15 will commence [41832/12]

Photo of Ruairi QuinnRuairi Quinn (Dublin South East, Labour)
Link to this: Individually | In context | Oireachtas source

The major building project for the school referred to by the Deputy was included in the 5 year construction programme announced in March. The project is at an early stage of architectural planning and is scheduled to proceed to tender and construction in 2013.