Written answers

Tuesday, 2 October 2012

Department of An Taoiseach

Cross-Border Projects

Photo of Joe McHughJoe McHugh (Donegal North East, Fine Gael)
Link to this: Individually | In context | Oireachtas source

To ask the Taoiseach if he will provide an update on the commitment to progressing the co-funded A5 road project; if he will further provide an update on the engagement that he has had with the Northern Ireland Executive in respect of this co-funded project; and if he will make a statement on the matter. [41269/12]

Photo of Enda KennyEnda Kenny (Mayo, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Transport is one of the areas of cooperation under the North South Ministerial Council (NSMC) process. Regular meetings of the Transport Sectoral Council are held, where transport issues, including investment, are discussed. The next Transport Sectoral is due to take place on 5 October 2012.

In relation to the A5 cross-border roads project, as the Deputy will be aware in 2006 the previous Fianna Fáil led Government gave a commitment to co-fund the construction of the A5. However, they made no provision to meet the costs of the A5 post 2012 in either the Four Year Plan or the Infrastructure Investment Priorities Plan 2010 to 2016. Given that £400 million sterling was due to fall between 2013 and 2016 and given the current state of the country’s Exchequer, it was not feasible to provide this level of funding in the coming years.

Therefore at the NSMC Plenary meeting on 8th November 2011, Ministers noted that the provision of further funding by the Irish Government for the A5 road was being deferred but that the Irish Government will provide £25m per annum in 2015 and 2016 towards the project. At the subsequent June 2012 NSMC Plenary meeting, it was noted that the N.I. Executive had announced an investment package of major roads including two sections of the A5 project. In addition it was noted that the Irish Government remains committed to the completion of the co-funded A5 project which is of strategic importance to the North West Region and the island as a whole, but that the Government is not in a position to making funding commitments for the period past 2016 in advance of its consideration of the next capital review framework. The NSMC Plenary did approve a funding implementation plan for the A5 project to the end of 2016 which incorporated the £50m committed by the Irish Government.