Written answers
Thursday, 11 November 2010
Department of Finance
Decentralisation Programme
6:00 pm
Denis Naughten (Roscommon-South Leitrim, Fine Gael)
Link to this: Individually | In context
Question 116: To ask the Minister for Finance further to Parliamentary Question No. 132 of 23 June 2009, the updated figures for the number of public servants decentralised to date in each project concerned; when the final transfer will be completed; and if he will make a statement on the matter. [42232/10]
Brian Lenihan Jnr (Dublin West, Fianna Fail)
Link to this: Individually | In context
A total of 3,407 staff have decentralised to 37 locations since the commencement of the programme.
Table 1 gives details of 31 projects in respect of which permanent accommodation has been procured or provided. A total of 2,232 staff have moved to take up positions at those locations.
Table 2 gives details of a further 3 sites where the contractual arrangements for the provision of permanent accommodation are already in place or are under active consideration. A total of 457 staff have already moved to advance offices in respect of these projects.
Table 3 gives details of 57 projects in 41 locations where contractual commitments for the provision of permanent accommodation have not yet been entered into. Advance parties totalling 718 staff are in place in temporary accommodation in respect of 16 of these projects. As already announced, decisions on the timing of implementation of the balance of these projects are deferred pending a review in 2011 in light of budgetary developments. The current economic environment and policies affecting overall public service numbers will impact on the timeframe for the completion of each project and the transfer of further staff to these locations.
Table 1 | |||
Decentralisation Projects where property is already completed | |||
Location | Organisation | Total posts to be decentralised | Staff moved to decentralising location to 10 November 2010 |
Athlone | Education & Skills | 88 | 88 |
Ballina | Road Safety Authority | 62 | 62 |
Buncrana | Social Protection | 102 | 100 |
Carrick-on-Shannon (Phase I) | Social Protection | 159 | 159 |
Clonakilty | Agriculture Fisheries & Food | 86 | 85 |
Clonakilty | BIM | 90 | 20 |
Clonakilty | Sea Fisheries Protection Authority | 47 | 47 |
Cork | HIQA | 100 | 47 |
Gaoth Dobhair | Foras Na Gaeilge | 5 | 5 |
Killarney | Tourism Culture & Sport | 103 | 79 |
Kilrush | Office of the Revenue Commissioners | 57 | 57 |
Limerick | Foreign Affairs | 134 | 134 |
Listowel | Office of the Revenue Commissioners | 52 | 52 |
Longford | Irish Prison Service | 133 | 133 |
Loughrea | Road Safety Authority | 40 | 40 |
Loughrea | Transport | 10 | 10 |
Naas | IAASA | 13 | 12 |
Na Forbacha | Community Equality and Gaeltacht Affairs | 13 | 12 |
Navan | Coroners Service | 4 | 4 |
Navan | Garda Civilian HR Division | 38 | 38 |
Navan | National Property Services Regulatory Authority | 9 | 9 |
Navan | Office of the Director of Probation Service | 15 | 15 |
Navan | Office of the Revenue Commissioners | 100 | 100 |
Newbridge | Defence | 201 | 162 |
Newbridge | Defence Forces | 43 | 55 |
Newcastlewest | Office of the Revenue Commissioners | 52 | 52 |
Sligo | Social Protection | 88 | 72 |
Tipperary Town | Private Security Agency | 32 | 32 |
Trim | Office of Public Works | 334 | 240 |
Tullamore | Finance | 130 | 122 |
Wexford | Environment Heritage & Local Government | 270 | 189 |
Total | 2,610 | 2,232 |
Table 2 | ||||
Priority Decentralisation Projects Approved by Government to Proceed | ||||
Location | Organisation | Total posts to be decentralised | Staff moved to decentralising location at 10 November 2010 | Property Update |
Portlaoise (HQ location) | Community Equality and Gaeltacht Affairs | 595 | 317 | Following the decision in December 2009 not to proceed with the PPP Midlands Bundle the Portlaoise project is to proceed on a traditional procurement basis. |
Roscommon | Property Registration Authority | 230 | 77 | The PRA is expected to move to the building early in the New Year, |
Tipperary Town | Justice and Law Reform | 186 | 63 | Construction Work due to start early December 2010 |
Total | 1,011 | 457 |
Table 3 | |||
Decentralisation Projects Deferred, Pending a Review in 2011* | |||
Location | Organisation | Staff moved to decentralising location to 10 November 2010 | Moves Deferred |
Arklow | NSAI | 124 | |
Athlone | Higher Education Authority | 64 | |
Athy (advance party in place) | Office of Revenue Commissioners | 73 | 180 |
Ballinasloe | National Roads Authority | 110 | |
Birr (advance party in place) | FÁS | 20 | 378 |
Carlow (advance party in place) | Enterprise Trade and Innovation | 103 | 257 |
Carrickmacross | Social Protection | 85 | |
Carrick on Shannon | Central Fisheries Board | 54 | |
Carrick on Shannon (Phase II) | Social Protection | 90 | |
Cavan (advance party in place) - HQ | Communications Energy & Natural Resources | 57 | 244 |
Cavan/Portlaoise/Galway | HIQA | 80 | |
Charlestown (advance party in Tubbercurry) | Community Equality & Gealtacht Affairs | 100 | 64 |
Claremorris (Phase I) | Office of Public Works | 31 | 104 |
Claremorris (Phase II) | Office of Public Works | 38 | |
Clifden (advance party in place) | Pobal | 25 | 17 |
Currage | Defence Forces | 413 | |
Donegal | Socail Protection | 258 | |
Drogheda | Transport | 37 | |
Drogheda | Citizens Information Board | 49 | |
Drogheda | Local Government Computer Service Board | 101 | |
Drogheda | Railway Safety Commission | 16 | |
Drogheda | Socail Protection | 499 | |
Dundalk (advance party in place) | Sustainable Energy Ireland | 11 | 23 |
Dungarvan | OSI | 206 | |
Edenderry | FETAC | 44 | |
Edenderry | HETAC | 34 | |
Edenderry | NQAI | 18 | |
Enniscorthy | Bord Bia | 76 | |
Fermoy | Agriculture Fisheries & Food | 100 | |
Gaoth Dobhair | Foras na Gaeilge | 25 | |
Kanturk | Office of Public Works | 88 | |
Kildare | Office of the Revenue Commissioners | 380 | |
Kildare | Finance - CMOD | 30 | |
Kilkenny | Environment Heritage & Local Government | 62 | |
Kilkenny | Arts Council | 49 | |
Killarney | Irish Sports Council | 31 | |
Macroom | Agriculture Fisheries & Food | 100 | |
Mallow | Fáilte Ireland | 163 | |
Mitchelstown | CIÉ Group | 200 | |
Monaghan | Combat Poverty Agency | 25 | |
Mullingar | Education & Skills | 7 | 290 |
Naas | Health Service Executive | 300 | |
New Ross | Environment Heritage & Local Government | 125 | |
Portarlington (advance party) | Data Protection Commissioner | 23 | 0 |
Portarlington (advance party in Portlaoise) | Equality Tribunal (civil service) | 8 | 34 |
Portarlington (advance party in Portlaoise) | NCCA (civil service) | 12 | 25 |
Portarlington | NEWB | 14 | |
Roscrea (advance party in place) | Equality Authority (civil service) | 16 | 25 |
Roscrea | Garda Ombudsman Commission | 23 | |
Shannon (advance party in place) | Enterprise Ireland** | 66 | 226 |
Shannon | Irish Aviation Authority | 102 | |
Thomastown (advance party in Kilkenny) | Health & Safety Authority | 33 | 83 |
Thurles (advance party in place) | Garda Headquarters CGVU & FCPS | 133 | 133 |
Waterford | Environment Heritage & Local Government | 225 | |
Wexford | National Building Agency | 63 | |
Youghal | Public Appointments Service | 100 | |
Youghal | Valuation Office | 100 | |
Total | 718 | 6,784 | |
*This Review will take account of the impact of the Rationalisation of State Agencies | |||
**Including 40 existing Shannon Development and EI posts located in Shannon as part of a parallel process. | |||
No comments