Written answers

Tuesday, 2 November 2010

Department of Education and Science

Schools Building Projects

9:00 pm

Photo of Michael McGrathMichael McGrath (Cork South Central, Fianna Fail)
Link to this: Individually | In context

Question 123: To ask the Tánaiste and Minister for Education and Skills the position regarding an application for phase two of a primary schools development (details supplied) in County Cork. [39774/10]

Photo of Mary CoughlanMary Coughlan (Donegal South West, Fianna Fail)
Link to this: Individually | In context

As the Deputy will be aware, the Phase I development of the school to which he refers was completed in June of last year under my Department's rapid delivery programme. My officials are currently undertaking some preliminary work on the proposed Phase II development. Officials from my Department will be touch with the school authorities shortly, in relation to progression of the project.

Photo of Michael McGrathMichael McGrath (Cork South Central, Fianna Fail)
Link to this: Individually | In context

Question 124: To ask the Tánaiste and Minister for Education and Skills the details of the revised tender arrangements to apply for the construction of a national school (details supplied) in County Cork and when she expects the project to move on site. [39776/10]

Photo of Mary CoughlanMary Coughlan (Donegal South West, Fianna Fail)
Link to this: Individually | In context

As the Deputy will be aware, the project to which he refers encountered delays in securing planning permission and land transfers. These problems were compounded by certain issues that subsequently arose with the preferred bidder and which resulted in a recent decision to re-tender the project. It is envisaged that the project will be re-tendered shortly. Subject to no issues arising, it is anticipated that it will progress to construction in early 2011.