Schools Building Projects

4:00 pm

Photo of Emmet StaggEmmet Stagg (Kildare North, Labour)
Link to this: Individually | In context

Question 268: To ask the Tánaiste and Minister for Education and Skills if she has received the supplementary report for a school (details supplied) in County Kildare; if a contractor has been chosen and if so when will construction commence. [27536/10]

Photo of Mary CoughlanMary Coughlan (Donegal South West, Fianna Fail)
Link to this: Individually | In context

My Department recently received the Supplementary Tender Report for the school to which the Deputy refers. However, my Department is still awaiting receipt of some outstanding documentation from the preferred bidder. When this documentation has been received and assuming that there are no issues arising, the contract can be awarded and the project will progress to construction.

Photo of Emmet StaggEmmet Stagg (Kildare North, Labour)
Link to this: Individually | In context

Question 269: To ask the Tánaiste and Minister for Education and Skills if tenders have been invited for the building of a school (details supplied) in County Kildare, the time frame for building the new school specified in the tender documents; and the closing date for receipt of tenders. [27537/10]

Photo of Mary CoughlanMary Coughlan (Donegal South West, Fianna Fail)
Link to this: Individually | In context

I am pleased to inform the Deputy that the project to which he refers is currently out to tender. The closing date for receipt of tenders is 2nd July. Once the project goes on site, the expected duration of the construction phase is 12 months.

Photo of Emmet StaggEmmet Stagg (Kildare North, Labour)
Link to this: Individually | In context

Question 270: To ask the Tánaiste and Minister for Education and Skills if the contract for the building of the extension to a school (details supplied) in County Kildare has been awarded; and when will construction commence. [27538/10]

Photo of Mary CoughlanMary Coughlan (Donegal South West, Fianna Fail)
Link to this: Individually | In context

My Department recently received the Supplementary Tender Report for the school to which the Deputy refers. However, my Department is still awaiting receipt of some outstanding documentation from the preferred bidder. When this documentation has been received and assuming that there are no issues arising, the contract can be awarded and the project will progress to construction.