Question 57: To ask the Minister for Defence his plans for vessel replacement in the Naval Service; and if he will make a statement on the matter. [15623/10]

Photo of Tony KilleenTony Killeen (Clare, Fianna Fail)
Link to this: Individually | In context

A vessel replacement strategy for the Naval Service is currently in progress following the commencement of a tender competition in 2007. The competition sought tenders for the purchase of two Offshore Patrol Vessels (OPVs), with an option for a third, and one Extended Patrol Vessel (EPV), with an option for a second. The process comprised two stages – Stage 1, a Request for Proposals and Stage 2, an Invitation to Tender.

During 2008, Stage 1 of the tender process was completed and, insofar as the OPVs are concerned, tenders were received in response to Stage 2. Following tender evaluation, a preferred bidder was selected last year and detailed and extensive contract negotiations are now very close to conclusion. The decision to proceed with the final award of contract to purchase the OPVs will be subject to Government approval and agreement on funding. Subject to such approval, delivery of the new vessels would be expected to commence on a phased basis from 2014.

This strategy combined with a continuous process of refurbishment and repair will ensure that the operational capability of the Naval Service is maintained at a satisfactory level. The acquisition of modern new vessels will ensure that the Service will be fully equipped to carry out its day to day roles in enforcing the State's sovereign rights over our waters and our fisheries and meeting Ireland's obligations in the area of maritime safety and security and fisheries protection.