Written answers

Tuesday, 2 March 2010

Department of Communications, Energy and Natural Resources

Alternative Energy Projects

12:00 pm

Photo of Bernard AllenBernard Allen (Cork North Central, Fine Gael)
Link to this: Individually | In context

Question 60: To ask the Minister for Communications, Energy and Natural Resources his plans to amend the Gate 3 system to facilitate commercially viable new wind farm proposals getting grid connection without unreasonable delay; and if he will make a statement on the matter. [10178/10]

Photo of Jack WallJack Wall (Kildare South, Labour)
Link to this: Individually | In context

Question 88: To ask the Minister for Communications, Energy and Natural Resources his plans to amend the Gate 3 system to facilitate commercially viable new wind farm proposals getting grid connection without unreasonable delay; and if he will make a statement on the matter. [10111/10]

Photo of Eamon RyanEamon Ryan (Dublin South, Green Party)
Link to this: Individually | In context

I propose to take Questions Nos. 60 and 88 together.

The Commission for Energy Regulation (CER) has statutory responsibility for grid connection offers and for oversight of EirGrid's grid connection process including the Gate process for renewable energy.

There is currently over 1,500 megawatts (MWs) of renewable generation capacity connected to the electricity grid. Wind powered technology is the dominant renewable technology. Over 100 individual windfarms have been connected with a combined capacity of 1,260 MWs. 240 MWs of hydro-power are connected. The balance represents biomass plants mainly landfill gas.

The contribution from renewable energy connected to the electricity grid is increasing very steadily from year to year. Renewable generation contributed 11.9% of all electricity consumed in 2008 compared to just 4.4% in 2003. Renewable generation in 2009 is estimated to have represented 14% of all generation consumed. Ireland is on schedule to meet the 15% target for electricity from renewable sources in 2010.

In addition to projects already built and connected, a further 1400 MWs of capacity have already signed grid connection offers from the Gate 1 and Gate 2 processes and will be built and connected to the grid over the next two or three year period.

The CER and EirGrid previously estimated that around 5,800 megawatts (MWs) of renewable capacity will be required in total to deliver the 40% target in 2020. If the downward trend in electricity consumption continues the prospects for exceeding the 40% target increases.

The CER decision on the 'Gate 3' round provides for connection offers for an additional 4,000 MWs of renewable electricity capacity. Approximately 90% of these offers are wind powered capacity including around 800 MW of offshore wind. The Gate 3 decisions, combined with existing renewable capacity and projects currently being built and connected, point to the 40% target being met and even exceeded by 2020. Ireland's National Renewable Energy Action Plan, which is to be submitted to the EU Commission by next June, will set out the detailed projections and strategies to achieve the national target. The plan is being developed in consultation with the renewable sector and all stakeholders.

The projects in Gate 3 were selected by the CER on a "first come first served" criterion. Grid connection offers for projects within the Gate 3 process began to issue in December last year. They continue to be issued on a phased basis until mid 2011.

To ensure this process operates efficiently and to keep the industry informed of developments, the CER has established a Gate 3 Liaison Group involving all stakeholders, including EirGrid and the renewable industry associations. The objective is to ensure the connection offer process is completed quickly, transparently and effectively.

The Gate 3 process was extensively consulted on by the CER. Through public consultation and dedicated industry workshops, all industry stakeholders were given the opportunity of responding in advance to the proposed connection process.

Once the level of take up of Gate 3 offers becomes clear, the CER will decide how to address any issues arising.

A strategic framework to deliver on the potential for exporting renewable electricity from Ireland is also a key priority. This will take account of grid technology developments, power flow management techniques and progressive interconnection with the UK and potentially Europe. In that context Ireland's membership of the North Seas Countries Offshore Grid Initiative and involvement in other EU offshore wind fora will ensure that Ireland is at the forefront of European developments in offshore renewable energy.

Comments

No comments

Log in or join to post a public comment.