Written answers
Tuesday, 3 November 2009
Department of Environment, Heritage and Local Government
Planning Issues
8:00 pm
Michael McGrath (Cork South Central, Fianna Fail)
Link to this: Individually | In context
Question 930: To ask the Minister for the Environment, Heritage and Local Government the number of cases with the strategic infrastructure division of An Bord Pleanála; and the number which have been awaiting a decision for at least six months, at least eight months, at least ten months and at least 12 months. [38021/09]
Michael McGrath (Cork South Central, Fianna Fail)
Link to this: Individually | In context
Question 931: To ask the Minister for the Environment, Heritage and Local Government the number of normal planning appeals currently with An Bord Pleanála which have been awaiting a decision for a period of at least six months, at least eight months, at least ten months and at least 12 months. [38022/09]
John Gormley (Dublin South East, Green Party)
Link to this: Individually | In context
I propose to take Questions Nos. 930 and 931 together.
To date the Strategic Infrastructure Division of An Bord Pleanála has received 30 formal applications for major strategic infrastructure projects under the provisions of the Planning and Development (Strategic Infrastructure) Act 2006, and 18 cases have been disposed of. There are 12 major Strategic Infrastructure cases currently on hand. The specific information sought in relation to 2009 is set out in the following table:
> 6 months | > 8 months | > 10 months | > 12 months | |
Strategic Infrastructure Cases on hands (as at 19 Oct, 2009): | 2 | 2 | 3 | 2 |
As of 19 October 2009, An Bord Pleanála had 1,506 normal planning cases on hand, a decrease of 45% compared to the same period in 2008. The specific information sought in relation to 2009 is set out in the following table:
> 6 months | > 8 months | > 10 months | > 12 months | |
Appeals on hands (as at 19 Oct, 2009): | 177 | 95 | 64 | 50 |
No comments