Written answers

Tuesday, 6 October 2009

Department of Education and Science

Schools Building Projects

9:00 pm

Photo of Michael CreedMichael Creed (Cork North West, Fine Gael)
Link to this: Individually | In context

Question 1116: To ask the Minister for Education and Science if his attention has been drawn to the condition of the roadway leading to a school (details supplied) in County Cork; if he has awarded all moneys due to the contractor in this case; if the approach road was included in his estimate for the works for the school; the steps, in view of the health and safety concerns raised, he will take to bring this matter to a satisfactory conclusion; and if he will make a statement on the matter. [33134/09]

Photo of Batt O'KeeffeBatt O'Keeffe (Cork North West, Fianna Fail)
Link to this: Individually | In context

The new site for the school referred to by the Deputy was acquired by the school Patron from a local developer as a result of a land swap. My Department has funded the construction of the new school. However, the project scope was predicated on the assurance that certain site development works and appropriate site access from the main road were to be carried out by the developer such as access road/path as part of the overall deal with the school Patron.

It has been brought to my attention that the developer has not, as yet, completed this work. I understand that the Board of Management of the school is engaging with the developer to progress the terms of their agreement. My officials are monitoring the situation.