Written answers

Thursday, 2 July 2009

Department of Education and Science

Schools Building Projects

Photo of Bernard DurkanBernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context

Question 211: To ask the Minister for Education and Science the current or expected position in regard to the provision of the new school and extra facilities required at Kill, County Kildare; the developmental procedures concluded or pending; when it is expected that all procedures will be finalised with a view to conclusion of the project in readiness for occupation; the projected date in this regard; and if he will make a statement on the matter. [27038/09]

Photo of Batt O'KeeffeBatt O'Keeffe (Cork North West, Fianna Fail)
Link to this: Individually | In context

I am pleased to inform the Deputy that the project to which he refers recently went on site and it is envisaged that the new school building will be complete in 12-15 months.

Photo of Bernard DurkanBernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context

Question 212: To ask the Minister for Education and Science when he expects to meet in full the application for major capital funding at a school (details supplied) in County Kildare; and if he will make a statement on the matter. [27039/09]

Photo of Batt O'KeeffeBatt O'Keeffe (Cork North West, Fianna Fail)
Link to this: Individually | In context

A major capital project delivering a new 8 classroom school was completed in 2006 for the school referred to by the Deputy. In 2007 the school in question received approval to build additional classrooms under the devolved Permanent Accommodation Scheme (PAS) and a grant on this basis was approved. The Board of Management was recently approved additional funding in relation to additional costs arising on the project. I understand that the project is ready to go to construction shortly.

Comments

No comments

Log in or join to post a public comment.