Written answers
Tuesday, 27 January 2009
Department of Agriculture and Food
Port Development
9:00 pm
Michael Creed (Cork North West, Fine Gael)
Link to this: Individually | In context
Question 1260: To ask the Minister for Agriculture, Fisheries and Food the progress made on the programme for Government proposal to maintain world-class fishery harbours at Castletownbere, Dunmore East, Howth, Killybegs, Rossaveel and Clogherhead; and if he will make a statement on the matter. [47724/08]
Brendan Smith (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context
The completion of the 2008 Fishery Harbour & Coastal Infrastructure Development Programme saw significant investment at both the six Fishery Harbour Centres (which now includes An Daingean) and various Local Authority owned harbours throughout the country.
The following table shows the funding provided to Fishery Harbour Centre projects under the 2008 Programme.
Fishery Harbours Centres | |
â'¬ | |
Safety & Maintenance | 1,485,643 |
Disability Access | 161,105 |
Castletownbere | |
Dinish wharf extension | 6,933,805 |
Effluent treatment | 18,904 |
Mainland quay extension | 195,394 |
RNLI Reclamation | 162,483 |
Dingle | |
Dingle harbour dredging | 63,058 |
Removal of slipway | 6,537 |
Berthing pontoons | 612,752 |
Dunmore East | |
Harbour Development | 49,838 |
Sedimentation Study | 41,272 |
Repairs East Pier II | 248,850 |
Erect safety railing | 5,691 |
Upgrade slipway | 22,615 |
Howth | |
Maintenance dredging | 27,636 |
Killybegs | |
Environmental Study | 96,051 |
Rossaveel | |
Gear Store Workshop | 633,154 |
Onshore works | 574,011 |
Ferry Pontoons | 1,761,212 |
11,453,263 |
My Department will continue to promote the development of the Fishery Harbours and Coastal Infrastructure within the constraints of available resources.
Michael Creed (Cork North West, Fine Gael)
Link to this: Individually | In context
Question 1261: To ask the Minister for Agriculture, Fisheries and Food the progress made on the programme for Government proposal to progress the major infrastructure projects in Cromane and Greencastle; and if he will make a statement on the matter. [47725/08]
Brendan Smith (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context
Cromane Harbour is owned by Kerry County Council which is responsible for its maintenance and development. My Department however allocated funding of €750,000 to Kerry County Council in 2008 in order to advance the development of the Harbour. Kerry County Council encountered delays in securing land required for the advancement of the project and were not in a position to draw down the funding allocation in 2008.
Phase 1 of the Greencastle Development involves the construction of a 290 metre long breakwater. By the end of 2008, the breakwater extended into the sea for a distance of over 100 metres and now reaches into much deeper water.
In total, €5,062,848.77 was spent on the Greencastle project in 2008. My Department contributed 75% of the total project cost (€3,797,136.58). The remaining 25% is to be contributed equally between Donegal County Council and the Department of Community, Rural & Gaeltacht Affairs with each committing 12.5% (€632,856.09).
Michael Creed (Cork North West, Fine Gael)
Link to this: Individually | In context
Question 1262: To ask the Minister for Agriculture, Fisheries and Food the progress made on the programme for Government proposal to ensure the full potential of each of the fisheries harbours here to be a unique and internationally recognised brand by Bord Iascaigh Mhara working with the fishermen's co-operatives, developing branded seafood products from those ports; and if he will make a statement on the matter. [47726/08]
Brendan Smith (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context
I am happy to report that Bord Iascaigh Mhara, the Sea Fisheries Board, the agency responsible for developing sustainable Irish Sea Fishing and Aquaculture industries, is currently actively engaging with co-operatives from the main Fishery Harbours and has put in place a comprehensive programme of work including: Seafood quality training for both co-op staff and members; and Developing key market analysis to ensure that each of the Fisheries Harbours realises their potential to be a unique and internationally recognised brand. The development of robust environment management systems is central to this process.
No comments