Question 690: To ask the Minister for Transport the completion date for each of the projects under the Transport 21 programme; and if he will make a statement on the matter. [30080/08]
Noel Dempsey (Meath West, Fianna Fail)
Link to this: Individually | In context
Transport 21 projects currently underway will be completed as set out in Table 1. Projects which have already been completed since the beginning of Transport 21 in 2006 are listed in Table 2.
The start and completion dates of projects which have not yet commenced will be determined by the funding allocation available during the current difficult economic climate. The commencement dates for these projects will also be influenced by the time taken for public consultation, the relevant statutory process and the procurement and contract award processes.
Table 1 | |
Project | Indicative Completion Date |
M50 Upgrade (Phase 1) | 2008 |
Cork commuter rail service to Midleton | 2009 |
Kildare rail upgrade | 2010 |
Table 2 | |
Project | Completion Date |
N2 Monaghan Town Bypass | 2006 |
Docklands Railway Station | 2007 |
New Portlaoise train depot | 2008 |