Electricity Generation

11:00 pm

Photo of Simon CoveneySimon Coveney (Cork South Central, Fine Gael)
Link to this: Individually | In context

Question 956: To ask the Minister for Communications, Energy and Natural Resources the amount of public funding his Department has provided since 2007 for the construction of a 400 MW gas-fired electricity generating station at Whitegate, Cork; the amount he will spend on such a project; when he expects the plant to come online; and if he will make a statement on the matter. [22748/08]

Photo of Eamon RyanEamon Ryan (Dublin South, Green Party)
Link to this: Individually | In context

Bord Gáis Éireann (BGÉ) is financing the construction of the 400 MW gas-fired electricity generating station at Whitegate, Cork, from its own resources. No funding has been or will be provided by my Department, for the project.

The cost of the project is €400 million and I am advised by BGÉ that the plant is on schedule for completion in July 2010.