Written answers
Tuesday, 17 June 2008
Department of Transport
Airport Development Projects
11:00 pm
Tommy Broughan (Dublin North East, Labour)
Link to this: Individually | In context
Question 448: To ask the Minister for Transport when he expects the tendering process for Terminal 2 at Dublin Airport to be completed; when work will commence on building Terminal 2; and if he will make a statement on the matter. [23546/08]
Noel Dempsey (Meath West, Fianna Fail)
Link to this: Individually | In context
Construction work on T2 began on the 1st October 2007 and will continue until late 2009. After decommissioning and testing the new terminal is due to open to the public in April 2010. Further information on the progress of the Terminal 2 project is available on DAA's website (www.dublinairportauthority.com).